Perlassery Sn 2 AE |
Date: 02/12/2024 |
Work has been completed | 100% Completed
Completed on 30/11/2024
Perlassery Sn 2 AE |
Date: 28/11/2024 |
Work in progress | 95% Completed
5165m pipe laid.215nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE)
Perlassery Sn 2 AE |
Date: 23/11/2024 |
Work in progress | 95% Completed
5165m pipe laid.210nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE)
Perlassery Sn 2 AE |
Date: 18/11/2024 |
Work in progress | 95% Completed
5165m pipe laid.201nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE)
Perlassery Sn 2 AE |
Date: 12/11/2024 |
Work in progress | 95% Completed
5165m pipe laid.173nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE)
Perlassery Sn 2 AE |
Date: 06/11/2024 |
Work in progress | 95% Completed
5165m pipe laid.137nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE)
Perlassery Sn 2 AE |
Date: 02/11/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.137Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 25/10/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.109 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 19/10/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 15/10/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 08/10/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 04/10/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 30/09/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 23/09/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 18/09/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 09/09/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 04/09/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 30/08/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 21/08/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 13/08/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 09/08/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 05/08/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 01/08/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 27/07/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 22/07/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 12/07/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 08/07/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 25/06/2024 |
Work in progress | 95% Completed
Work in progress | 95% Completed
Perlassery Sn 2 AE |
Date: 20/06/2024 |
Work in progress | 95% Completed
Work in progress | 95% Completed
Perlassery Sn 2 AE |
Date: 10/06/2024 |
Work in progress | 95% Completed
Work in progress | 95% Completed
Perlassery Sn 2 AE |
Date: 01/06/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 22/05/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 17/05/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted
Perlassery Sn 2 AE |
Date: 10/05/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided.
Perlassery Sn 2 AE |
Date: 25/04/2024 |
Work in progress | 95% Completed
95% work completed.5165m pipe laid.61 Nos.FHTC Provided.
Perlassery Sn 2 AE |
Date: 18/04/2024 |
Work in progress | 85% Completed
5165m pipe laid.61 Nos.FHTC Provided.
Perlassery Sn 2 AE |
Date: 08/04/2024 |
Work in progress | 85% Completed
5165m pipe laid.49nos. FHTC Provided.
Perlassery Sn 2 AE |
Date: 27/03/2024 |
Work in progress | 15% Completed
work in progress
Perlassery Sn 2 AE |
Date: 18/03/2024 |
Work in progress | 5% Completed
work in progress
Perlassery Sn 2 AE |
Date: 11/03/2024 |
Work in progress | 3% Completed
work in progress
Perlassery Sn 2 AE |
Date: 28/02/2024 |
Work has started | 0% Completed
Pipe have been supplied.
Kannur PH Dn EE |
Date: 14/02/2024 |
Work has started | 0% Completed
WORK ORDER ISSUED
Perlassery Sn 2 AE |
Date: 06/02/2024 |
Work in progress | 0% Completed
WORK ORDER ISSUED
Perlassery Sn 2 AE |
Date: 29/01/2024 |
Work has started | 0% Completed
WORK ORDER ISSUED
Kannur PH Dn EE |
Date: 08/01/2024 |
Work has started | 0% Completed
WORK ORDER ISSUED
Kannur PH Dn EE |
Date: 21/12/2023 |
Work has started | 0% Completed
WORK TENDERED
Kannur PH Dn EE |
Date: 20/12/2023 |
Work has started | 0% Completed
TS ISSUED