| Thalassery PH Sn AE |
| Date: 14/11/2023 |
Work has been completed | 100% Completed
Final bill submitted
| Thalassery PH Sn AE |
| Date: 08/11/2023 |
Work has been completed | 100% Completed
Work completed & final bill under preparation
| Thalassery PH Sn AE |
| Date: 03/11/2023 |
Work has been completed | 100% Completed
Work completed & final bill under preparation
| Thalassery PH Sn AE |
| Date: 27/10/2023 |
Work has been completed | 100% Completed
Work completed & final bill under preparation
| Thalassery PH Sn AE |
| Date: 20/10/2023 |
Work has been completed | 100% Completed
Work completed & final bill under preparation
| Thalassery PH Sn AE |
| Date: 11/10/2023 |
Work has been completed | 100% Completed
Work completed
| Thalassery PH Sn AE |
| Date: 03/10/2023 |
Work has been completed | 100% Completed
Work completed
| Thalassery PH Sn AE |
| Date: 27/09/2023 |
Work has been completed | 100% Completed
Work completed
| Thalassery PH Sn AE |
| Date: 23/09/2023 |
| Thalassery PH Sn AE |
| Date: 18/09/2023 |
Work in progress | 70% Completed
Pipe line laying & connection work completed
| Thalassery PH Sn AE |
| Date: 12/09/2023 |
Work in progress | 70% Completed
Pipe line laying & connection work completed
| Thalassery PH Sn AE |
| Date: 06/09/2023 |
Work in progress | 70% Completed
Pipe line laying & connection work completed
| Thalassery PH Sn AE |
| Date: 01/09/2023 |
| Thalassery PH Sn AE |
| Date: 24/08/2023 |
| Thalassery PH Sn AE |
| Date: 19/08/2023 |
| Thalassery PH Sn AE |
| Date: 15/08/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 10/08/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 07/08/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 01/08/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 25/07/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 18/07/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 14/07/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 11/07/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 04/07/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 30/06/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 26/06/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 19/06/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 14/06/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission and 8nos HTC Completed
| Thalassery PH Sn AE |
| Date: 08/06/2023 |
Work in progress | 10% Completed
220m Pipe line laid and Laying of GI Pipe along PWD road pending for want PWD Road cutting permission
| Thalassery PH Sn AE |
| Date: 01/06/2023 |
Work has started | 0% Completed
Supplied order placed for pvc pipes
| Thalassery PH Sn AE |
| Date: 25/05/2023 |
Work in progress | 0% Completed
Supplied order placed for pvc pipes
| Kannur PH Dn EE |
| Date: 29/03/2023 |
Work has started | 0% Completed
agreement executed