Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kozhikode Project Dn AE5
Date: 22/09/2021

Work has been completed | 100% Completed

Work completed, Total expenditure Rs.40652452/- final Bill paid to contractor on 26.02.2021 including Road restoration charges .

Kozhikode Project Dn AE2
Date: 21/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 19/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 17/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 15/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 12/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 08/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 07/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 05/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 03/04/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 31/03/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 29/03/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 27/03/2021

Work has been completed | 100% Completed

work completed

Kozhikode Project Dn AE2
Date: 25/03/2021

Work has been completed | 100% Completed

work has been completed

Kozhikode Project Dn AE2
Date: 23/03/2021

Work has been completed | 100% Completed

work has been completed

Kozhikode Project Dn AE2
Date: 18/03/2021

Work has been completed | 100% Completed

work has been completed

Kozhikode Project Dn AE2
Date: 15/03/2021

Work has been completed | 100% Completed

work has been completed

Kozhikode Project Dn AE2
Date: 08/03/2021

Work has been completed | 100% Completed

work has been completed

Kozhikode Project Dn AE2
Date: 03/03/2021

Work has been completed | 100% Completed

Work completed

Kozhikode Project Dn AE2
Date: 23/02/2021

Work has been completed | 100% Completed

work completed, final bill submitted

Kozhikode Project Dn AE2
Date: 17/11/2020

Work has been completed | 100% Completed

Completed

Kozhikode Project Dn AE2
Date: 09/09/2020

Work in progress | 99% Completed

Pipe Laying completed. Interconnection and road reformation work in progress (BT road 3km, Concrete road 7km, 30 nos of interconnection and 6km pipe line charging work are to be done) Total length of pipes: 110mm PVC pipe- 38370m and 100mm GI pipe 500m)

Attached images

img img img

Kozhikode Project Dn AE2
Date: 18/08/2020

Work in progress | 98% Completed

Pipe Laying completed. Interconnection and road reformation work in progress (BT road 3km, Concrete road 7km, 60 nos of interconnection and 9km pipe line charging work are to be done) Total length of pipes: 110mm PVC pipe- 38370m and 100mm GI pipe 500m)

Kozhikode Project Dn AE2
Date: 14/08/2020

Work in progress | 97% Completed

Supplying,laying and Testing of 110mm PVC pipe 38000m out of 38370m,&100mm GI pipe 100m out of 500m

Kozhikode Project Dn AE2
Date: 01/07/2020

Work in progress | 96% Completed

Supplying,laying and Testing of 110mm PVC pipe 37400m out of 38370m,&100mm GI pipe 100m out of 500m