Kozhikode Project Dn AE5 |
Date: 22/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.40652452/- final Bill paid to contractor on 26.02.2021 including Road restoration charges .
Kozhikode Project Dn AE2 |
Date: 21/04/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 19/04/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 17/04/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 15/04/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 12/04/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 08/04/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 07/04/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 05/04/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 03/04/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 31/03/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 29/03/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 27/03/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 25/03/2021 |
Work has been completed | 100% Completed
work has been completed
Kozhikode Project Dn AE2 |
Date: 23/03/2021 |
Work has been completed | 100% Completed
work has been completed
Kozhikode Project Dn AE2 |
Date: 18/03/2021 |
Work has been completed | 100% Completed
work has been completed
Kozhikode Project Dn AE2 |
Date: 15/03/2021 |
Work has been completed | 100% Completed
work has been completed
Kozhikode Project Dn AE2 |
Date: 08/03/2021 |
Work has been completed | 100% Completed
work has been completed
Kozhikode Project Dn AE2 |
Date: 03/03/2021 |
Work has been completed | 100% Completed
Work completed
Kozhikode Project Dn AE2 |
Date: 23/02/2021 |
Work has been completed | 100% Completed
work completed, final bill submitted
Kozhikode Project Dn AE2 |
Date: 17/11/2020 |
Work has been completed | 100% Completed
Completed
Kozhikode Project Dn AE2 |
Date: 09/09/2020 |
Work in progress | 99% Completed
Pipe Laying completed. Interconnection and road reformation work in progress (BT road 3km, Concrete road 7km, 30 nos of interconnection and 6km pipe line charging work are to be done) Total length of pipes: 110mm PVC pipe- 38370m and 100mm GI pipe 500m)
Attached images
Kozhikode Project Dn AE2 |
Date: 18/08/2020 |
Work in progress | 98% Completed
Pipe Laying completed. Interconnection and road reformation work in progress (BT road 3km, Concrete road 7km, 60 nos of interconnection and 9km pipe line charging work are to be done) Total length of pipes: 110mm PVC pipe- 38370m and 100mm GI pipe 500m)
Kozhikode Project Dn AE2 |
Date: 14/08/2020 |
Work in progress | 97% Completed
Supplying,laying and Testing of 110mm PVC pipe 38000m out of 38370m,&100mm GI pipe 100m out of 500m
Kozhikode Project Dn AE2 |
Date: 01/07/2020 |
Work in progress | 96% Completed
Supplying,laying and Testing of 110mm PVC pipe 37400m out of 38370m,&100mm GI pipe 100m out of 500m