Koothuparambu PH Sn AE |
Date: 27/03/2025 |
Work in progress | 88% Completed
Dismantling of old pump house completed.compound wall work in progress. 583m pipe laid.
Koothuparambu PH Sn AE |
Date: 19/03/2025 |
Work in progress | 85% Completed
Dismantling of pumphouse to be done.
Koothuparambu PH Sn AE |
Date: 05/03/2025 |
Work in progress | 42% Completed
Pumphouse plastering completed.Painting to be done.530m pipe laid.
Koothuparambu PH Sn AE |
Date: 03/02/2025 |
Work in progress | 42% Completed
Pumphouse roof slab concrete completed.348m pipe line lied.
Koothuparambu PH Sn AE |
Date: 31/01/2025 |
Work in progress | 42% Completed
Pumphouse roof slab concrete completed
Koothuparambu PH Sn AE |
Date: 18/01/2025 |
Work in progress | 40% Completed
Construction of pumphouse-55% completed. KSEB LT Line shifted.
Koothuparambu PH Sn AE |
Date: 07/01/2025 |
Work in progress | 40% Completed
Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.
Koothuparambu PH Sn AE |
Date: 31/12/2024 |
Work in progress | 40% Completed
Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.
Koothuparambu PH Sn AE |
Date: 18/12/2024 |
Work in progress | 20% Completed
Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.
Koothuparambu PH Sn AE |
Date: 10/12/2024 |
Work in progress | 20% Completed
Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.
Koothuparambu PH Sn AE |
Date: 03/12/2024 |
Work in progress | 20% Completed
Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.
Koothuparambu PH Sn AE |
Date: 26/11/2024 |
Work in progress | 20% Completed
Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.
Koothuparambu PH Sn AE |
Date: 19/11/2024 |
Work in progress | 20% Completed
Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.
Koothuparambu PH Sn AE |
Date: 13/11/2024 |
Work in progress | 20% Completed
Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.
Koothuparambu PH Sn AE |
Date: 02/11/2024 |
Work in progress | 20% Completed
3.554 KM Pipeline completed.
Koothuparambu PH Sn AE |
Date: 25/10/2024 |
Work in progress | 20% Completed
Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.
Koothuparambu PH Sn AE |
Date: 19/10/2024 |
Work in progress | 18% Completed
Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.
Koothuparambu PH Sn AE |
Date: 15/10/2024 |
Work in progress | 18% Completed
Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted. Pipe laying started.
Koothuparambu PH Sn AE |
Date: 07/10/2024 |
Work in progress | 16% Completed
Lintel and sunshade concreting completed.
Koothuparambu PH Sn AE |
Date: 01/10/2024 |
Work in progress | 15% Completed
Laterite masonry work started.
Koothuparambu PH Sn AE |
Date: 24/09/2024 |
Work in progress | 14% Completed
Tie beam and slab concrete completed.
Koothuparambu PH Sn AE |
Date: 18/09/2024 |
Work in progress | 13% Completed
Column concrete completed.
Koothuparambu PH Sn AE |
Date: 11/09/2024 |
Work in progress | 10% Completed
Plinth beam concrete completed
Koothuparambu PH Sn AE |
Date: 06/09/2024 |
Work in progress | 5% Completed
Foundation earth filling completed.