Koothuparambu PH Sn AE
Date: 27/03/2025

Work in progress | 88% Completed

Dismantling of old pump house completed.compound wall work in progress. 583m pipe laid.

Koothuparambu PH Sn AE
Date: 19/03/2025

Work in progress | 85% Completed

Dismantling of pumphouse to be done.

Koothuparambu PH Sn AE
Date: 05/03/2025

Work in progress | 42% Completed

Pumphouse plastering completed.Painting to be done.530m pipe laid.

Koothuparambu PH Sn AE
Date: 03/02/2025

Work in progress | 42% Completed

Pumphouse roof slab concrete completed.348m pipe line lied.

Koothuparambu PH Sn AE
Date: 31/01/2025

Work in progress | 42% Completed

Pumphouse roof slab concrete completed

Koothuparambu PH Sn AE
Date: 18/01/2025

Work in progress | 40% Completed

Construction of pumphouse-55% completed. KSEB LT Line shifted.

Koothuparambu PH Sn AE
Date: 07/01/2025

Work in progress | 40% Completed

Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.

Koothuparambu PH Sn AE
Date: 31/12/2024

Work in progress | 40% Completed

Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.

Koothuparambu PH Sn AE
Date: 18/12/2024

Work in progress | 20% Completed

Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.

Koothuparambu PH Sn AE
Date: 10/12/2024

Work in progress | 20% Completed

Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.

Koothuparambu PH Sn AE
Date: 03/12/2024

Work in progress | 20% Completed

Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.

Koothuparambu PH Sn AE
Date: 26/11/2024

Work in progress | 20% Completed

Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.

Koothuparambu PH Sn AE
Date: 19/11/2024

Work in progress | 20% Completed

Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.

Koothuparambu PH Sn AE
Date: 13/11/2024

Work in progress | 20% Completed

Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.

Koothuparambu PH Sn AE
Date: 02/11/2024

Work in progress | 20% Completed

3.554 KM Pipeline completed.

Koothuparambu PH Sn AE
Date: 25/10/2024

Work in progress | 20% Completed

Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.

Koothuparambu PH Sn AE
Date: 19/10/2024

Work in progress | 18% Completed

Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted.

Koothuparambu PH Sn AE
Date: 15/10/2024

Work in progress | 18% Completed

Construction of pumphouse-55% completed. Work has been temporarily stopped as KSEB LT Line situated above the pumphouse has to be shifted. Pipe laying started.

Koothuparambu PH Sn AE
Date: 07/10/2024

Work in progress | 16% Completed

Lintel and sunshade concreting completed.

Koothuparambu PH Sn AE
Date: 01/10/2024

Work in progress | 15% Completed

Laterite masonry work started.

Koothuparambu PH Sn AE
Date: 24/09/2024

Work in progress | 14% Completed

Tie beam and slab concrete completed.

Koothuparambu PH Sn AE
Date: 18/09/2024

Work in progress | 13% Completed

Column concrete completed.

Koothuparambu PH Sn AE
Date: 11/09/2024

Work in progress | 10% Completed

Plinth beam concrete completed

Koothuparambu PH Sn AE
Date: 06/09/2024

Work in progress | 5% Completed

Foundation earth filling completed.