Koothuparamba Proj AE 2 |
Date: 01/06/2021 |
Work has been completed | 100% Completed
completed ,commissioned
Koothuparamba Proj AE 2 |
Date: 03/04/2021 |
Work has been completed | 100% Completed
Completed and Final Bill submitted
Koothuparamba Proj AE 2 |
Date: 16/11/2020 |
Work has been completed | 100% Completed
Work completed
Koothuparamba Proj AE 2 |
Date: 14/09/2020 |
Work in progress | 98% Completed
Pipe line work complted and regular water supply started.new house connection in progress.
Koothuparamba Proj AE 2 |
Date: 24/08/2020 |
Work in progress | 97% Completed
Out of 17.825kms pipe line 17.750kms completed and commissioned. 300nos old house connections reconnected with this line and 146 nos of new connections given. Balance house connection work is in progress.