Edappal PH Dn EE |
Date: 30/10/2024 |
Work has started | 0% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 06/08/2024 |
Work in progress | 13% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 02/08/2024 |
Work in progress | 13% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 30/07/2024 |
Work in progress | 13% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 23/08/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 12/08/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 05/08/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 03/08/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 01/08/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 21/07/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 12/07/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 06/07/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 27/06/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 21/06/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 18/06/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 14/06/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 09/06/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 02/06/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 27/05/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 21/05/2022 |
Work in progress | 12% Completed
s reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 17/05/2022 |
Work in progress | 12% Completed
s reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 13/05/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 04/05/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 28/04/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 24/04/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 23/04/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 18/04/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 08/04/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 30/03/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 19/03/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 07/03/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 28/02/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 23/02/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 19/02/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 17/02/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 14/02/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 07/02/2022 |
Work in progress | 12% Completed
As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan
Edappal Sn AE |
Date: 01/02/2022 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 31/01/2022 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 30/01/2022 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 29/01/2022 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 28/01/2022 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 27/01/2022 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 20/01/2022 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 11/01/2022 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 03/01/2022 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 28/12/2021 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 21/12/2021 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 16/12/2021 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 13/12/2021 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 09/12/2021 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 04/12/2021 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 01/12/2021 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 29/11/2021 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 22/11/2021 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 17/11/2021 |
Work in progress | 1% Completed
Estimate under preparation based on new rate
Edappal Sn AE |
Date: 12/11/2021 |
Work in progress | 0% Completed
Estimate under preparation
Edappal Sn AE |
Date: 08/11/2021 |
Work in progress | 0% Completed
Estimate under preparation
Edappal Sn AE |
Date: 28/10/2021 |
Work in progress | 0% Completed
Estimate to be finalised after approval of PVC pipe rates
Edappal Sn AE |
Date: 21/10/2021 |
Work in progress | 0% Completed
Estimate to be finalised after approval of PVC pipe rates
Edappal Sn AE |
Date: 14/10/2021 |
Work in progress | 0% Completed
Estimate to be finalised after approval of PVC pipe rates
Edappal Sn AE |
Date: 07/10/2021 |
Work in progress | 0% Completed
Estimate to be finalised after approval of PVC pipe rates
Edappal PH Dn EE |
Date: 30/09/2021 |
Work has started | 0% Completed
Estimate to be finalised after approval of PVC pipe rates.