Edappal PH Dn EE
Date: 30/10/2024

Work has started | 0% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 06/08/2024

Work in progress | 13% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 02/08/2024

Work in progress | 13% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 30/07/2024

Work in progress | 13% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 23/08/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 12/08/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 05/08/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 03/08/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 01/08/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 21/07/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 12/07/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 06/07/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 27/06/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 21/06/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 18/06/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 14/06/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 09/06/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 02/06/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 27/05/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 21/05/2022

Work in progress | 12% Completed

s reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 17/05/2022

Work in progress | 12% Completed

s reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 13/05/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 04/05/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 28/04/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 24/04/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 23/04/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 18/04/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 08/04/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 30/03/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 19/03/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 07/03/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 28/02/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 23/02/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 19/02/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 17/02/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 14/02/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 07/02/2022

Work in progress | 12% Completed

As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5th SLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan

Edappal Sn AE
Date: 01/02/2022

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 31/01/2022

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 30/01/2022

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 29/01/2022

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 28/01/2022

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 27/01/2022

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 20/01/2022

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 11/01/2022

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 03/01/2022

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 28/12/2021

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 21/12/2021

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 16/12/2021

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 13/12/2021

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 09/12/2021

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 04/12/2021

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 01/12/2021

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 29/11/2021

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 22/11/2021

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 17/11/2021

Work in progress | 1% Completed

Estimate under preparation based on new rate

Edappal Sn AE
Date: 12/11/2021

Work in progress | 0% Completed

Estimate under preparation

Edappal Sn AE
Date: 08/11/2021

Work in progress | 0% Completed

Estimate under preparation

Edappal Sn AE
Date: 28/10/2021

Work in progress | 0% Completed

Estimate to be finalised after approval of PVC pipe rates

Edappal Sn AE
Date: 21/10/2021

Work in progress | 0% Completed

Estimate to be finalised after approval of PVC pipe rates

Edappal Sn AE
Date: 14/10/2021

Work in progress | 0% Completed

Estimate to be finalised after approval of PVC pipe rates

Edappal Sn AE
Date: 07/10/2021

Work in progress | 0% Completed

Estimate to be finalised after approval of PVC pipe rates

Edappal PH Dn EE
Date: 30/09/2021

Work has started | 0% Completed

Estimate to be finalised after approval of PVC pipe rates.