Mattannur Project Sn 2 AE
Date: 10/07/2022

Work has been completed | 100% Completed

Survey work completed

Mattannur Project Sn 2 AE
Date: 09/07/2022

Work has been completed | 100% Completed

Survey work completed

Mattannur Project Sn 2 AE
Date: 08/07/2022

Work in progress | 95% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 07/07/2022

Work in progress | 80% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 06/07/2022

Work in progress | 80% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 05/07/2022

Work in progress | 80% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 04/07/2022

Work in progress | 80% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 03/07/2022

Work in progress | 80% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 02/07/2022

Work in progress | 80% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 01/07/2022

Work in progress | 80% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 30/06/2022

Work in progress | 80% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 29/06/2022

Work in progress | 80% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 28/06/2022

Work in progress | 78% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 27/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 26/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 25/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 24/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 23/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 22/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 21/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 20/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 19/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 18/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 17/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 16/06/2022

Work in progress | 75% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 15/06/2022

Work in progress | 70% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 14/06/2022

Work in progress | 70% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 13/06/2022

Work in progress | 70% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 12/06/2022

Work in progress | 70% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 11/06/2022

Work in progress | 70% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 10/06/2022

Work in progress | 70% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 09/06/2022

Work in progress | 68% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 08/06/2022

Work in progress | 68% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 07/06/2022

Work in progress | 65% Completed

Work is in progress

Mattannur Project Sn 2 AE
Date: 06/06/2022

Work in progress | 65% Completed

Work is in progress

Mattannur Project Sn 2 AE
Date: 05/06/2022

Work in progress | 60% Completed

Work is in progress

Mattannur Project Sn 2 AE
Date: 04/06/2022

Work in progress | 60% Completed

Work order issued to Surya Construction

Mattannur Project Sn 2 AE
Date: 03/06/2022

Work in progress | 60% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 25/05/2022

Work in progress | 40% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 15/05/2022

Work in progress | 25% Completed

Survey work is in progress

Mattannur Project Sn 2 AE
Date: 05/05/2022

Work in progress | 10% Completed

Survey work is in progress