Kalliassery W S Section - AE |
Date: 03/07/2025 |
Work in progress | 76% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 13/05/2025 |
Work in progress | 76% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 08/05/2025 |
Work in progress | 76% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 27/03/2025 |
Work in progress | 76% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 06/03/2025 |
Work in progress | 76% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 19/02/2025 |
Work in progress | 76% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 04/02/2025 |
Work in progress | 76% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 27/01/2025 |
Work in progress | 76% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 20/01/2025 |
Work in progress | 76% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 15/01/2025 |
Work in progress | 76% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 01/01/2025 |
Work in progress | 75% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 18/12/2024 |
Work in progress | 75% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 26/11/2024 |
Work in progress | 75% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 11/11/2024 |
Work in progress | 75% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 08/11/2024 |
Work in progress | 75% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 04/11/2024 |
Work in progress | 75% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 30/10/2024 |
Work in progress | 75% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 22/10/2024 |
Work in progress | 75% Completed
144m of 110mm PVC pipe laid
Kalliassery W S Section - AE |
Date: 19/10/2024 |
Work in progress | 50% Completed
Work started on 08/10/2024. 60 % pipe laid.
Kalliassery W S Section - AE |
Date: 16/10/2024 |
Work in progress | 50% Completed
Work started on 08/10/2024. 60 % pipe laid.
Kalliassery W S Section - AE |
Date: 09/10/2024 |
Work in progress | 50% Completed
Work started on 08/10/2024. 60 % pipe laid.
Kalliassery W S Section - AE |
Date: 05/10/2024 |
Work has started | 0% Completed
Site handed over to the contractor on 10/08/2024
Kalliassery W S Section - AE |
Date: 26/09/2024 |
Work has started | 0% Completed
Site handed over to the contractor on 10/08/2024
Kalliassery W S Section - AE |
Date: 19/09/2024 |
Work has started | 0% Completed
Site handed over to the contractor on 10/08/2024
Thaliparamba WS Dn EE |
Date: 10/09/2024 |
Work has started | 0% Completed
Site handed over to the contractor on 10/08/2024