Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kalpetta PH Sn 2 - AE
Date: 24/08/2022

Work has been completed | 100% Completed

Bill Scrutinizing in Sub Division

Sulthan Bathery PH Dn EE
Date: 17/08/2022

Work has been completed | 100% Completed

Bill Submitted

Kalpetta PH Sn 2 - AE
Date: 11/08/2022

Work has been completed | 100% Completed

Bill Submitted

Kalpetta PH Sn 2 - AE
Date: 29/07/2022

Work has been completed | 100% Completed

Work completed on 26.07.2022 and Bill under preparation

Kalpetta PH Sub Dn - AEE
Date: 24/07/2022

Work in progress | 20% Completed

The house connection ,pipe laying ,file works for the house connection etc in progress. The work will complete in this week.

Kalpetta PH Sub Dn - AEE
Date: 19/07/2022

Work in progress | 19% Completed

The work delaying due to rain

Kalpetta PH Sub Dn - AEE
Date: 14/07/2022

Work in progress | 9% Completed

The work delaying due to rain.

Kalpetta PH Sub Dn - AEE
Date: 09/07/2022

Work in progress | 7% Completed

The work delaying due to rain.

Kalpetta PH Sub Dn - AEE
Date: 04/07/2022

Work in progress | 6% Completed

The work delaying due to rain.

Kalpetta PH Sub Dn - AEE
Date: 29/06/2022

Work in progress | 5% Completed

Work started and the house connection works in progress

Kalpetta PH Sub Dn - AEE
Date: 20/06/2022

Work has started | 0% Completed

Planning to start the work in the available area of Athirathil colony in Thariyode panchayath.

Kalpetta PH Sub Dn - AEE
Date: 16/06/2022

Work has started | 0% Completed

Letter ( last letter dtd 31.05.2022) sent to Secretary Thariode Panchayath in order to get the resolution for to change the list of beneficiaries since the originally proposed connections were already covered in the JJM phase-1 works in this area. The resolution not get from the Panchayath.

Sulthan Bathery PH Dn EE
Date: 13/06/2022

Work in progress | 0% Completed

Letter ( last letter dtd 31.05.2022) sent to Secretary Thariode Panchayath in order to get the resolution for the FHTCs since the originally proposed connections were already covered in the JJM phase-1 works in this area..

Kalpetta PH Sub Dn - AEE
Date: 10/06/2022

Work has started | 0% Completed

Letter ( last letter dtd 31.05.2022) sent to Secretary Thariode Panchayath in order to get the resolution for the FHTCs since the originally proposed connections were already covered in the JJM phase-1 works in this area..

Kalpetta PH Sub Dn - AEE
Date: 07/06/2022

Work has started | 0% Completed

Letter ( last letter dtd 31.05.2022) sent to Secretary Thariode Panchayath in order to get the resolution for the FHTCs since the originally proposed connections were already covered in the JJM phase-1 works in this area..

Kalpetta PH Sub Dn - AEE
Date: 02/06/2022

Work in progress | 41% Completed

Letter ( last letter dtd 31.05.2022) sent to Secretary Thariode Panchayath in order to get the resolution for the FHTCs.

Sulthan Bathery PH Dn EE
Date: 31/05/2022

Work in progress | 40% Completed

Panchayath resolution was not obtained

Kalpetta PH Sn 2 - AE
Date: 25/05/2022

Work in progress | 40% Completed

Proposed area is completed under JJM. Panchayath resolution not getting to changing the work and Letter sent to Panchayat and letter attached in file or document

Sulthan Bathery PH Dn EE
Date: 18/05/2022

Work in progress | 40% Completed

Proposed area is completed under JJM. Panchayath resolution not getting to changing the work

Sulthan Bathery PH Dn EE
Date: 25/04/2022

Work in progress | 1% Completed

Proposed area is completed under JJM. Hence new area will be done under this work

Sulthan Bathery PH Dn EE
Date: 31/03/2022

Work in progress | 1% Completed

Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022. Warning letter issued on 10.03.2022.

Sulthan Bathery PH Dn EE
Date: 23/03/2022

Work in progress | 1% Completed

Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022. Warning letter issued on 10.03.2022.

Sulthan Bathery PH Dn EE
Date: 17/03/2022

Work in progress | 1% Completed

Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022. Warning letter issued on 10.03.2022.

Sulthan Bathery PH Dn EE
Date: 11/03/2022

Work in progress | 1% Completed

Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022. Warning letter issued on 10.03.2022.

Sulthan Bathery PH Dn EE
Date: 03/03/2022

Work in progress | 1% Completed

Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022.

Sulthan Bathery PH Dn EE
Date: 26/02/2022

Work in progress | 1% Completed

Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022.

Sulthan Bathery PH Dn EE
Date: 15/02/2022

Work in progress | 1% Completed

Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022.

Sulthan Bathery PH Dn EE
Date: 09/02/2022

Work in progress | 1% Completed

Work is not started due to non-availability of pipes as reported by contractor. Letter issued to contractor on 20.01.2022.