| Kalpetta PH Sn 2 - AE |
| Date: 24/08/2022 |
Work has been completed | 100% Completed
Bill Scrutinizing in Sub Division
| Sulthan Bathery PH Dn EE |
| Date: 17/08/2022 |
Work has been completed | 100% Completed
Bill Submitted
| Kalpetta PH Sn 2 - AE |
| Date: 11/08/2022 |
Work has been completed | 100% Completed
Bill Submitted
| Kalpetta PH Sn 2 - AE |
| Date: 29/07/2022 |
Work has been completed | 100% Completed
Work completed on 26.07.2022 and Bill under preparation
| Kalpetta PH Sub Dn - AEE |
| Date: 24/07/2022 |
Work in progress | 20% Completed
The house connection ,pipe laying ,file works for the house connection etc in progress. The work will complete in this week.
| Kalpetta PH Sub Dn - AEE |
| Date: 19/07/2022 |
Work in progress | 19% Completed
The work delaying due to rain
| Kalpetta PH Sub Dn - AEE |
| Date: 14/07/2022 |
Work in progress | 9% Completed
The work delaying due to rain.
| Kalpetta PH Sub Dn - AEE |
| Date: 09/07/2022 |
Work in progress | 7% Completed
The work delaying due to rain.
| Kalpetta PH Sub Dn - AEE |
| Date: 04/07/2022 |
Work in progress | 6% Completed
The work delaying due to rain.
| Kalpetta PH Sub Dn - AEE |
| Date: 29/06/2022 |
Work in progress | 5% Completed
Work started and the house connection works in progress
| Kalpetta PH Sub Dn - AEE |
| Date: 20/06/2022 |
Work has started | 0% Completed
Planning to start the work in the available area of Athirathil colony in Thariyode panchayath.
| Kalpetta PH Sub Dn - AEE |
| Date: 16/06/2022 |
Work has started | 0% Completed
Letter ( last letter dtd 31.05.2022) sent to Secretary Thariode Panchayath in order to get the resolution for to change the list of beneficiaries since the originally proposed connections were already covered in the JJM phase-1 works in this area. The resolution not get from the Panchayath.
| Sulthan Bathery PH Dn EE |
| Date: 13/06/2022 |
Work in progress | 0% Completed
Letter ( last letter dtd 31.05.2022) sent to Secretary Thariode Panchayath in order to get the resolution for the FHTCs since the originally proposed connections were already covered in the JJM phase-1 works in this area..
| Kalpetta PH Sub Dn - AEE |
| Date: 10/06/2022 |
Work has started | 0% Completed
Letter ( last letter dtd 31.05.2022) sent to Secretary Thariode Panchayath in order to get the resolution for the FHTCs since the originally proposed connections were already covered in the JJM phase-1 works in this area..
| Kalpetta PH Sub Dn - AEE |
| Date: 07/06/2022 |
Work has started | 0% Completed
Letter ( last letter dtd 31.05.2022) sent to Secretary Thariode Panchayath in order to get the resolution for the FHTCs since the originally proposed connections were already covered in the JJM phase-1 works in this area..
| Kalpetta PH Sub Dn - AEE |
| Date: 02/06/2022 |
Work in progress | 41% Completed
Letter ( last letter dtd 31.05.2022) sent to Secretary Thariode Panchayath in order to get the resolution for the FHTCs.
| Sulthan Bathery PH Dn EE |
| Date: 31/05/2022 |
Work in progress | 40% Completed
Panchayath resolution was not obtained
| Kalpetta PH Sn 2 - AE |
| Date: 25/05/2022 |
Work in progress | 40% Completed
Proposed area is completed under JJM. Panchayath resolution not getting to changing the work and Letter sent to Panchayat and letter attached in file or document
| Sulthan Bathery PH Dn EE |
| Date: 18/05/2022 |
Work in progress | 40% Completed
Proposed area is completed under JJM. Panchayath resolution not getting to changing the work
| Sulthan Bathery PH Dn EE |
| Date: 25/04/2022 |
Work in progress | 1% Completed
Proposed area is completed under JJM. Hence new area will be done under this work
| Sulthan Bathery PH Dn EE |
| Date: 31/03/2022 |
Work in progress | 1% Completed
Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022. Warning letter issued on 10.03.2022.
| Sulthan Bathery PH Dn EE |
| Date: 23/03/2022 |
Work in progress | 1% Completed
Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022. Warning letter issued on 10.03.2022.
| Sulthan Bathery PH Dn EE |
| Date: 17/03/2022 |
Work in progress | 1% Completed
Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022. Warning letter issued on 10.03.2022.
| Sulthan Bathery PH Dn EE |
| Date: 11/03/2022 |
Work in progress | 1% Completed
Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022. Warning letter issued on 10.03.2022.
| Sulthan Bathery PH Dn EE |
| Date: 03/03/2022 |
Work in progress | 1% Completed
Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022.
| Sulthan Bathery PH Dn EE |
| Date: 26/02/2022 |
Work in progress | 1% Completed
Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022.
| Sulthan Bathery PH Dn EE |
| Date: 15/02/2022 |
Work in progress | 1% Completed
Work is not started due to non-delivery of pipes in small quantities by suppliers, as reported by contractor. Letter issued to contractor on 20.01.2022.
| Sulthan Bathery PH Dn EE |
| Date: 09/02/2022 |
Work in progress | 1% Completed
Work is not started due to non-availability of pipes as reported by contractor. Letter issued to contractor on 20.01.2022.