Kozhikode Project Dn AE5 |
Date: 22/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.12012960/- final Bill paid to contractor on 30.01.2021 including Road restoration charges .
Kozhikode Project Dn AE5 |
Date: 01/09/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 21/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 19/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 17/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 15/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 12/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 08/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 07/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 05/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 03/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 31/03/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 29/03/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 27/03/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 25/03/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 23/03/2021 |
Work has been completed | 100% Completed
work has been completed
Kozhikode Project Dn AE2 |
Date: 18/03/2021 |
Work has been completed | 100% Completed
work has been completed
Kozhikode Project Dn AE2 |
Date: 15/03/2021 |
Work has been completed | 100% Completed
work has been completed
Kozhikode Project Dn AE2 |
Date: 08/03/2021 |
Work has been completed | 100% Completed
work has been completed
Kozhikode Project Dn AE2 |
Date: 03/03/2021 |
Work has been completed | 100% Completed
Work completed
Kozhikode Project Dn AE2 |
Date: 23/02/2021 |
Work has been completed | 100% Completed
work completed , final bill submitted
Kozhikode Project Dn AE2 |
Date: 10/11/2020 |
Kozhikode Project Dn AE2 |
Date: 09/09/2020 |
Work in progress | 99% Completed
Pipe Laying completed. Interconnection and road reformation work in progress (BT road 5km, Concrete road 0.5km, 12 nos of interconnection and 2.5km pipe line charging work are to be done) Total length of pipes: 110mm PVC pipe- 12844m and 100mm GI pipe 250m)
Attached images
Kozhikode Project Dn AE2 |
Date: 18/08/2020 |
Work in progress | 98% Completed
Pipe Laying completed. Interconnection and road reformation work in progress (BT road 5km, Concrete road 1km, 15 nos of interconnection and 3.09km pipe line charging work are to be done) Total length of pipes: 110mm PVC pipe- 12844m and 100mm GI pipe 250m)
Kozhikode Project Dn AE2 |
Date: 14/08/2020 |
Work in progress | 97% Completed
Road restoration work in progress
Kozhikode Project Dn AE2 |
Date: 01/07/2020 |
Work in progress | 96% Completed
Supplying Laying and Testing of 110mm PVC pipe for a length of 12600m out of 12844m & 100mm GI Pipe for a length of 160m out of 250m.