State Plan 2023-24-SWS-131- Optimisation of Production and transmission CARWSS to Kadangode and Adjoining panchayaths-Supplying and fitting soft Starter Instead of DamagedSl ippering starter and supplying and fitting UG cable at kondayur Pump house
Project |
State Plan 2023-24-SWS-131- Optimisation of Production and transmission CARWSS to Kadangode and Adjoining panchayaths-Supplying and fitting soft Starter Instead of DamagedSl ippering starter and supplying and fitting UG cable at kondayur Pump house |
Project Code |
TCRGOK092315165 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
State Plan 2023-24-SWS-131- Optimisation of Production and transmission CARWSS to Kadangode and Adjoining panchayaths-Supplying and fitting soft Starter Instead of DamagedSl ippering starter and supplying and fitting UG cable at kondayur Pump house |
Status |
Completed |
District |
Thrissur |
Executing Office |
Vadakanchery PH Sn |
AS Amount (Rs) |
1000000
|
AS Number |
KWA-JB/176/2023-DCE 1-PIU-Part(1) |
TS Amount (Rs) |
260000 |
TS Number |
21716/2023_26_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
|
Population Benefitted |
1000 |
Capacity in MLD |
0.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
CARWSS to kadangode Adj panchayath Kondayur |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan 2023-24-SWS-131- Optimisation of Production and transmission CARWSS to Kadangode and Adjoining panchayaths-Supplying and fitting soft Starter Instead of DamagedSl ippering starter and supplying and fitting UG cable at kondayur Pump house (civil)-package 2 |
Vadakanchery PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Dec 2023 |
PKG 2 work completed |
Thrissur PH Dn EE |
|
15 Dec 2023 |
Work in progress |
Thrissur PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
21/10/2023 |
Scheduled date of Completion of the Project |
20 Jan 2024 |
Expected date of Completion |
20/01/2024 |
Processing Dates
AS Date |
02 Sep 2023 |
TS Date |
04 Oct 2023 |