Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Deposit work (2021-2022)- JIlla Panchayath- Providing water supply scheme to Kanalkunnu - Thottamoola in Noolpuzha GP

Project Deposit work (2021-2022)- JIlla Panchayath- Providing water supply scheme to Kanalkunnu - Thottamoola in Noolpuzha GP
Project Code WYDDEPO032212226P1
Type Package
Main Project Deposit Work(2021-22)- Jilla Panchayath- Providing water supply scheme to Kanalkunnu- Thottamoola in Noolpuzha GrAMA panchayath
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work (2021-2022)- JIlla Panchayath- Providing water supply scheme to Kanalkunnu - Thottamoola in Noolpuzha GP
Status On-going
District Wayanad
Executing Office Sulthan Bathery Sn
Agreement Number
Agreement Date
TS Amount (Rs) 2500000
TS Number TS/2022-2023/2022/9026
Technical specification Providing water supply scheme to Kanalkunnu - Thottamoola in Noolpuzha GP
Contractor Raju N.K (Mob: 9847617813)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/08/2022
Scheduled date of Completion as per agreement 15 Mar 2023
Expected date of Completion 12/11/2022

Processing Dates

TS Date 15 Jul 2022
Estimate Approval 26 Mar 2022
NIT Approval 26 Mar 2022
Tender Closing 30 Jul 2022
Technichal Pre-Qualification 30 Jul 2022
Price bid opening 23 Jul 2022

Approval Dates

Workorder Date 12 Aug 2022
NA 16 Sep 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sulthan Bathery PH Dn EE
Date: 20/12/2023

Work has been completed | 100% Completed

Work completed and Bill submitted..

Sulthan Bathery PH Dn EE
Date: 19/12/2023

Work in progress | 97% Completed

Awaiting Power connection. Fee paid to KSEB..