Project | Deposit work (2021-2022)- JIlla Panchayath- Providing water supply scheme to Kanalkunnu - Thottamoola in Noolpuzha GP |
---|---|
Project Code | WYDDEPO032212226P1 |
Type | Package |
Main Project | Deposit Work(2021-22)- Jilla Panchayath- Providing water supply scheme to Kanalkunnu- Thottamoola in Noolpuzha GrAMA panchayath |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Deposit work (2021-2022)- JIlla Panchayath- Providing water supply scheme to Kanalkunnu - Thottamoola in Noolpuzha GP |
Status | On-going |
District | Wayanad |
Executing Office | Sulthan Bathery Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 2500000 |
TS Number | TS/2022-2023/2022/9026 |
Technical specification | Providing water supply scheme to Kanalkunnu - Thottamoola in Noolpuzha GP |
Contractor | Raju N.K (Mob: 9847617813) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 12/08/2022 |
---|---|
Scheduled date of Completion as per agreement | 15 Mar 2023 |
Expected date of Completion | 12/11/2022 |
TS Date | 15 Jul 2022 |
---|---|
Estimate Approval | 26 Mar 2022 |
NIT Approval | 26 Mar 2022 |
Tender Closing | 30 Jul 2022 |
Technichal Pre-Qualification | 30 Jul 2022 |
Price bid opening | 23 Jul 2022 |
Workorder Date | 12 Aug 2022 |
---|---|
NA | 16 Sep 2022 |
Sulthan Bathery PH Dn EE |
Date: 20/12/2023 |
Work has been completed | 100% Completed
Work completed and Bill submitted..
Sulthan Bathery PH Dn EE |
Date: 19/12/2023 |
Work in progress | 97% Completed
Awaiting Power connection. Fee paid to KSEB..