- Home
- DEPOSIT-Deposit work Kanjikuzhy Panchaya...
DEPOSIT-Deposit work Kanjikuzhy Panchayath--permanent disconnection of existing public Taps( 163 Nos ) at Kanjikuzhy Panchayath -
Project |
DEPOSIT-Deposit work Kanjikuzhy Panchayath--permanent disconnection of existing public Taps( 163 Nos ) at Kanjikuzhy Panchayath - |
Project Code |
ALPDEPO122213575 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT-Deposit work Kanjikuzhy Panchayath--permanent disconnection of existing public
Taps( 163 Nos ) at Kanjikuzhy Panchayath - |
Status |
Completed |
District |
Alappuzha |
Executing Office |
Cherthala PH Sn |
AS Amount (Rs) |
258000
|
AS Number |
4705/2022 |
TS Amount (Rs) |
258000 |
TS Number |
10692/2022-2023 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
10 |
Capacity in MLD |
107.00 |
Actual Project Completion Date |
19 Apr 2023 |
Coverage |
Kanjikuzhy panchayath area |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work -Kanjikuzhy Panchayath--permanent disconnection of existing public Taps( 163 Nos ) at Kanjikuzhy Panchayath |
Cherthala PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Aug 2023 |
Final bill submitted to Division Office |
Cherthala PH Section - AE |
|
27 Jul 2023 |
Final bill submitted to Division Office |
Cherthala PH Section - AE |
|
12 Jul 2023 |
Bill under scrutiny in Sub Divison |
Cherthala PH SUb Dn |
|
22 Jun 2023 |
Final bill |
Cherthala PH Section - AE |
|
01 Jun 2023 |
100% |
Cherthala PH Section - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/02/2023 |
Scheduled date of Completion of the Project |
20 Apr 2023 |
Expected date of Completion |
22/04/2023 |
Processing Dates
AS Date |
20 Dec 2022 |
TS Date |
11 Jan 2023 |