DEPOSIT-DEPOSIT WORK - 2018 -19 - NTPC :- RWSS TO CHINGOLI - CONSTRUCTION OF TEMPORARY PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY & ERECTION OF PUMP SET AND COMMISSIONING NEW TUBE WELL BASED WSS NEAR SAMSKARIKA NILAYAM IN CHINGOLI PANCHAYAT.
Project |
DEPOSIT-DEPOSIT WORK - 2018 -19 - NTPC :- RWSS TO CHINGOLI - CONSTRUCTION OF TEMPORARY PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY & ERECTION OF PUMP SET AND COMMISSIONING NEW TUBE WELL BASED WSS NEAR SAMSKARIKA NILAYAM IN CHINGOLI PANCHAYAT. |
Project Code |
ALPDEPO022213272 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
This estimate is prepared as per letter No. A3-1718/17 dtd. 04/12/2017 of Chingoli
Panchayat. The original proposal is commissioning of RO plant of capacity 5000 LPH.
To ensure water availability in RO unit, tube well is to be commissioned. New tube well
was drilled by GWD Near Samskrika Nilayam in Chingoli Panchayat. This estimate
prepared for commissioning a new tube well scheme. As per direction of Executive
Engineer, estimate for RO unit is prepared as a separate estimate. So, to commission a
new scheme, detailed estimate is prepared. Items included in this estimate are as
follows.
1 APPENDIX A :- PART I - APPENDIX A - PART 1 :- CIVIL WORK - CONSTRUCTION
OF TEMPORARY PUMP HOUSE
2.APPENDIX A :- PART II - CONSTRUCTION OF PUMP HOUSE - ELECTRIFICATION
WORK.
3.APPENDIX B :- PART I - LAYING PUMPING MAIN - WORKING CHARGES
4.APPENDIX B :- PART II - LAYING PUMPING MAIN - COST OF MATERIALS
5.APPENDIX C :-SUPPLY, ERECTION AND COMMISSIONING OF SUBMERSIBLE
PUMP SET
6.APPENDIX D :- POWER ALLOCATION CHARGES TO KSEB. |
Status |
Completed |
District |
Alappuzha |
Executing Office |
Harippad PH Sn |
AS Amount (Rs) |
850000
|
AS Number |
5(1)-09/02/2022 |
TS Amount (Rs) |
850000 |
TS Number |
ORDER No. WRD/KWA-CE(CR)/EST_TS/11204/2022_26_1_1 Dated: 22-12-2022 |
Total Bill Submitted (Rs) |
601054 |
Total Bill Paid (Rs) |
601054 |
Population Benefitted |
15000 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Chingoli & Adjoining Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-DEPOSIT WORK - 2018 -19 - NTPC :- RWSS TO CHINGOLI - CONSTRUCTION OF TEMPORARY PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY & ERECTION OF PUMP SET AND COMMISSIONING NEW TUBE WELL BASED WSS NEAR SAMSKARIKA NILAYAM IN CHINGOLI PANCHAYAT. |
Harippad PH Sn |
|
2 |
DEPOSIT-DEPOSIT WORK - 2018 -19 - NTPC :- RWSS TO CHINGOLI - CONSTRUCTION OF TEMPORARY PUMP HOUSE, LAYING PUMPING MAIN, SUPPLY & ERECTION OF PUMP SET AND COMMISSIONING NEW TUBE WELL BASED WSS NEAR SAMSKARIKA NILAYAM IN CHINGOLI PANCHAYAT. |
Harippad PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
27 Mar 2023 |
Work completed and bill submitted |
Harippad PH Sn - AE |
|
27 Mar 2023 |
Work in progress |
Harippad PH Sn - AE |
|
23 Mar 2023 |
Work in progress |
Harippad PH Sn - AE |
|
20 Mar 2023 |
Work in progress |
Alappuzha PH Dn EE |
|
16 Mar 2023 |
Work in progress |
Harippad PH Sn - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
05/01/2023 |
Scheduled date of Completion of the Project |
04 Jul 2023 |
Expected date of Completion |
31/03/2023 |
Processing Dates
AS Date |
09 Feb 2022 |
TS Date |
09 Feb 2022 |