Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Deposit work of Nedumangad Block Panchayath-Annual Plan-2020-Central Finance Commision Grant for Urban Agglomeration- Placing protective fencing around Aruvikkara Reservoir and cleaning of the reservoir

Project Deposit work of Nedumangad Block Panchayath-Annual Plan-2020-Central Finance Commision Grant for Urban Agglomeration- Placing protective fencing around Aruvikkara Reservoir and cleaning of the reservoir
Project Code TVMDEPO12207998
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work of Nedumangad Block Panchayath-Annual Plan-2020-Central Finance Commision Grant for Urban Agglomeration- Placing protective fencing around Aruvikkara Reservoir and cleaning of the reservoir-On the south bank up to chainage 400 m & on North bank of chainange 1000m to 2500m
Status Completed
District Thiruvananthapuram
Executing Office Aruvikkara Sn 4
AS Amount (Rs) 15000000
AS Number 1416/B.P.2/2020/NDD
TS Amount (Rs) 15000000
TS Number 703,7304/2021-2022
Total Bill Submitted (Rs) 14144218
Total Bill Paid (Rs) 14144218
Population Benefitted 4500
Capacity in MLD 86.00
Actual Project Completion Date Date is not specified
Coverage fencing-On the south bank up to chainage 400 m & on North bank of chainange 1000m to 2500m
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work of Nedumangad Block Panchayath-Annual Plan-2020-Central Finance Commision Grant for Urban Agglomeration- Placing protective fencing around Aruvikkara Reservoir and cleaning of the reservoir-On the south bank up to chainage 400 m Aruvikkara Sn 4
2 Nedumangad Block Panchayath-Annual plan 2020 Central Finance commission Grant for Urban Agglomeration -Placing protective fencing around Aruvikkara Reservoir on North Bank of Chainage 1000m to 2500 m Aruvikkara Sn 4

Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Feb 2022 North Bank - Plastering work completed for about 1000m. Steel reinforcement progressing on remaining 500m for providing belt concrete. South Bank - Plastering work Progressing Aruvikkara Sn 4 AE
21 Dec 2021 Work restarted and rubble work progressing Aruvikkara Sn 4 AE
09 Nov 2021 Unable to proceed the work due to persistent rain and shortage of rubble. District Collector has issued orders stopping all types of quarrying. Aruvikkara Sn 4 AE
31 Oct 2021 Unable to proceed the work due to persistent rain and shortage of rubble. District Collector has issued orders stopping all types of quarrying Aruvikkara Sn 4 AE
05 Oct 2021 Jungle Clearing progressing Aruvikkara Sn 4 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 06/09/2021
Scheduled date of Completion of the Project 07 Feb 2022
Expected date of Completion 15/03/2022

Processing Dates

AS Date 22 Dec 2020
TS Date 06 Aug 2021

Other details

Project Officers View