State plan 2018-19-WSS Akalakunnam, Mutholi &Kozhuvanal- Supply and erection of Raw water & Clear Water Pump set for new scheme

Project State plan 2018-19-WSS Akalakunnam, Mutholi &Kozhuvanal- Supply and erection of Raw water & Clear Water Pump set for new scheme
Project Code KTMGOK0818606
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Supply and erection of 50HP VT-2 No at Raw water Pump House, 125 HP CF-2 NOS at Clear Water Pumphouse and 35 HP CF -2 NOS , 15 HP CF -2 NOS, 20 HP CF -2 NOS at Edamula Boosting Station.
Status On-going
District Kottayam
Executing Office Kottayam Project Dn
AS Amount (Rs) 15000000
AS Number G.O(Rt.)615/2018/WRD
TS Amount (Rs) 10600000
TS Number TS/2019-2020/2019/1074
Total Bill Submitted (Rs) 5610379
Total Bill Paid (Rs) 4984219
Population Benefitted 53332
Capacity in MLD 10.00
Actual Project Completion Date 30 Nov 2021
Coverage Akalakkunnam, Mutholi&Kozhuvanal Panchayat
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State plan 2018-19-WSS Akalakunnam, Mutholi &Kozhuvanal- Supply and erection of Raw water & Clear Water Pump set for new scheme Kottayam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Aug 2022 Supply and erection of pump set completed. Kottayam AE 3
07 Nov 2021 No quotes received. Hence due date extended. E-Tender to be opened on 09.11.2021. Kottayam Project Dn EE
28 Oct 2021 Estimate revised with 2018 DSR and new tender floated with Ref No.06/EE/PDK/2021-22.Bid opening date 03.11.2021. Kottayam Project Dn EE
02 Oct 2021 Header pipe in the pumphouse has to be shifted outside for which separate work was e-tendered. But no quotes received. Hence the TS is cancelled and estimate handed over for revising with 2018 DSR. After finishing this work only this ongoing work can be completed. Kottayam Project Dn EE
30 Aug 2021 No work Kottayam Project Dn AE2

Project Review

See All Review messages
Review Date Review Message Review Attended By
03 Feb 2021 Status Wrongly entered as work completed. Add package,AS details ,photos of pumpsets supplied ,officers and all details . AE

Duration & Sanction dates

Date of start of Project 06/07/2020
Scheduled date of Completion of the Project 05 Apr 2021
Expected date of Completion 30/09/2022

Processing Dates

AS Date 20 Aug 2018
TS Date 13 Nov 2019