- Home
- AMRUT -2016-17,2017-18 WSS to Guruvayur...
AMRUT -2016-17,2017-18 WSS to Guruvayur Municipality in Thrissur District-Improvement of water supply system for Guruvayur - Package I & II (Revised AS -81.34Cr)
Project |
AMRUT -2016-17,2017-18 WSS to Guruvayur Municipality in Thrissur District-Improvement of water supply system for Guruvayur - Package I & II (Revised AS -81.34Cr) |
Project Code |
TCRAMRUT0917546 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
Components:
1 ) Construction of Intake well cum Pump House
2 ) Construction of Water Treatment Plant
3) Raw Water Pumping Main - 600/500mm DI, 630mm HDPE
4) Transformers - 500KVA
5) Pumpsets - Raw Water and Clear Water |
Status |
Completed |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
813400000
|
AS Number |
GO(Rt) No. 3170/2017/LSGD |
TS Amount (Rs) |
737400000 |
TS Number |
TS/CE/CR/KWA/65/17-18 |
Total Bill Submitted (Rs) |
613705000 |
Total Bill Paid (Rs) |
613705000 |
Population Benefitted |
84587 |
Capacity in MLD |
15.00 |
Actual Project Completion Date |
31 Dec 2022 |
Coverage |
Guruvayoor Muncipality
Total area - 29.66km2
Benefitted Population - 84587 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-WSS to Guruvayur Muncipality -Construction of steel bridge at Chirakkal for laying 600mm DI Pipe |
Nattika Project Dn |
|
2 |
Improvement of water supply system for Guruvayur - Package II - Phase I |
Nattika Project Dn |
|
3 |
Improvement of water supply system for Guruvayur - Package II - Phase II |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Oct 2023 |
Work completed. |
Nattika Project Dn |
|
20 Oct 2023 |
Package I - Work completed. Package II - RWPM-39Km pipe laying completed.Chirakkal bridge-Steel fabrication, pipe line works and welding works are completed. |
Nattika Project Dn |
|
10 Oct 2023 |
Package I - Work completed except electric connection in WTP. Package II - RWPM-39Km pipe laying completed.Chirakkal bridge-Steel fabrication, pipe line works and welding works are completed, valve fixing works are ongoing. |
Nattika Project Dn |
|
27 Sep 2023 |
Package I - Work completed except electric connection in WTP. Package II - RWPM-38 Km pipe laying completed out of 39Km.Chirakkal bridge-Steel fabrication and welding works are completed,pipe line works are ongoing. |
Nattika Project Dn |
|
21 Sep 2023 |
Package I - Work completed except electric connection in WTP. Package II - RWPM-38 Km pipe laying completed out of 39Km.Chirakkal bridge-Steel fabrication and welding works are completed. |
Nattika Project Dn |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
04/09/2018 |
Scheduled date of Completion of the Project |
03 Mar 2020 |
Expected date of Completion |
31/07/2023 |
Processing Dates
AS Date |
28 Sep 2017 |
TS Date |
29 Jan 2018 |