AMRUT -2016-17,2017-18 WSS to Guruvayur Municipality in Thrissur District-Improvement of water supply system for Guruvayur - Package I & II (Revised AS -81.34Cr)

Project AMRUT -2016-17,2017-18 WSS to Guruvayur Municipality in Thrissur District-Improvement of water supply system for Guruvayur - Package I & II (Revised AS -81.34Cr)
Project Code TCRAMRUT0917546
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Components: 1 ) Construction of Intake well cum Pump House 2 ) Construction of Water Treatment Plant 3) Raw Water Pumping Main - 600/500mm DI, 630mm HDPE 4) Transformers - 500KVA 5) Pumpsets - Raw Water and Clear Water
Status Completed
District Thrissur
Executing Office Nattika Project Dn
AS Amount (Rs) 813400000
AS Number GO(Rt) No. 3170/2017/LSGD
TS Amount (Rs) 737400000
TS Number TS/CE/CR/KWA/65/17-18
Total Bill Submitted (Rs) 613705000
Total Bill Paid (Rs) 613705000
Population Benefitted 84587
Capacity in MLD 15.00
Actual Project Completion Date 31 Dec 2022
Coverage Guruvayoor Muncipality Total area - 29.66km2 Benefitted Population - 84587
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT-WSS to Guruvayur Muncipality -Construction of steel bridge at Chirakkal for laying 600mm DI Pipe Nattika Project Dn
2 Improvement of water supply system for Guruvayur - Package II - Phase I Nattika Project Dn
3 Improvement of water supply system for Guruvayur - Package II - Phase II Nattika Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Oct 2023 Work completed. Nattika Project Dn
20 Oct 2023 Package I - Work completed. Package II - RWPM-39Km pipe laying completed.Chirakkal bridge-Steel fabrication, pipe line works and welding works are completed. Nattika Project Dn
10 Oct 2023 Package I - Work completed except electric connection in WTP. Package II - RWPM-39Km pipe laying completed.Chirakkal bridge-Steel fabrication, pipe line works and welding works are completed, valve fixing works are ongoing. Nattika Project Dn
27 Sep 2023 Package I - Work completed except electric connection in WTP. Package II - RWPM-38 Km pipe laying completed out of 39Km.Chirakkal bridge-Steel fabrication and welding works are completed,pipe line works are ongoing. Nattika Project Dn
21 Sep 2023 Package I - Work completed except electric connection in WTP. Package II - RWPM-38 Km pipe laying completed out of 39Km.Chirakkal bridge-Steel fabrication and welding works are completed. Nattika Project Dn

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 04/09/2018
Scheduled date of Completion of the Project 03 Mar 2020
Expected date of Completion 31/07/2023

Processing Dates

AS Date 28 Sep 2017
TS Date 29 Jan 2018

Other details