State Plan 2021-22 TSS - Increasing capacity of 150mm SW pipe to 200 mm SW pipe and constructing RCC manholes at Koopakkaramadom
Project |
State Plan 2021-22 TSS - Increasing capacity of 150mm SW pipe to 200 mm SW pipe and constructing RCC manholes at Koopakkaramadom |
Project Code |
TVMGOK05217491 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
State Plan 2021-22 TSS - Increasing capacity of 150mm SW pipe to 200 mm SW pipe and constructing RCC manholes at Koopakkaramadom |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Kuriathy Sewerage Sn 1 |
AS Amount (Rs) |
1100000
|
AS Number |
KWA/JB/PIU1/AE1/12/2021 (II) |
TS Amount (Rs) |
1090000 |
TS Number |
12663/2021-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
100 |
Capacity in MLD |
0.01 |
Actual Project Completion Date |
12 Feb 2022 |
Coverage |
Koopakarimadam lane near Subhash nagar in Perumthanni ward |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan 2021-22 TSS - Increasing capacity of 150mm SW pipe to 200 mm SW pipe and constructing RCC manholes at Koopakkaramadom |
Kuriathy Sewerage Sn 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
12 Feb 2022 |
Work Completed. |
Kuriathy Sewerage Sn1 AE |
|
09 Feb 2022 |
98 % : Pipe laying completed (85m/85m). 2 extra manholes constructed as per site condition (Total 7 MHs). Restoration work completed. 2 MH covers fixed. MH cover received, shifted to site and fixing in progress. |
Kuriathy Sewerage Sn1 AE |
|
07 Feb 2022 |
96% : Pipe laying completed (85m/85m). 2 extra manholes constructed as per site condition (Total 7 MHs). Restoration work completed. 2 MH covers fixed, 5 nos. to be fixed. Cover supply delayed due to shortage of materials. Expected to reach site by 08/02/2022. |
Kuriathy Sewerage Sn1 AE |
|
04 Feb 2022 |
95% : Pipe laying completed (85m/85m). 2 extra manholes constructed as per site condition (Total 7 MHs). Restoration work completed. 2 MH covers fixed, 5 nos. to be fixed. Covers expected by 05/02/2022. |
Kuriathy Sewerage Sn1 AE |
|
01 Feb 2022 |
95% : Pipe laying completed (85m/85m). 2 extra manholes constructed as per site condition (Total 7 MHs). Restoration work completed. 2 MH covers fixed, 5 nos. to be fixed. Covers expected by 02/02/2022. |
Kuriathy Sewerage Sn1 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
02/12/2021 |
Scheduled date of Completion of the Project |
31 Mar 2022 |
Expected date of Completion |
31/03/2022 |
Processing Dates
AS Date |
14 May 2021 |
TS Date |
08 Nov 2021 |