22 RWSS - NABARD - ASSISTED - RDWSS to Puthukkad, Parappukkara and adjoining panchayaths - Supply, erection, testing, commissioning and maintaining of 250KVA/11KV/433V outdoor transformer at raw water pump house.

Project 22 RWSS - NABARD - ASSISTED - RDWSS to Puthukkad, Parappukkara and adjoining panchayaths - Supply, erection, testing, commissioning and maintaining of 250KVA/11KV/433V outdoor transformer at raw water pump house.
Project Code TCRNABARD05148226
Type Main project
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme
Description 22 RWSS - NABARD - ASSISTED - RDWSS to Puthukkad, Parappukkara and adjoining panchayaths - Supply, erection, testing, commissioning and maintaining of 250KVA/11KV/433V outdoor transformer at raw water pump house.
Status Completed
District Thrissur
Executing Office Nattika Project Dn
AS Amount (Rs) 95700000
AS Number KWA/HO/WN/06/2014-15
TS Amount (Rs)
TS Number TS/CE/CR/KWA/09/2015-16
Total Bill Submitted (Rs) 2190211
Total Bill Paid (Rs) 2190211
Population Benefitted
Capacity in MLD 6.00
Actual Project Completion Date Date is not specified
Coverage Pudukkad, Alagappanagar and Parappukkara (Part) Panchayaths

Packages

No. Project Name Location View
1 22 RWSS - NABARD - ASSISTED - RDWSS to Puthukkad, Parappukkara and adjoining panchayaths - Supply, erection, testing, commissioning and maintaining of 250KVA/11KV/433V outdoor transformer at raw water pump house. Nattika Project Dn

No status have been added to this project

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 25/01/2019
Scheduled date of Completion of the Project 07 Sep 2018
Expected date of Completion 29/04/2019

Processing Dates

AS Date 31 May 2014
TS Date 04 Nov 2015

Other details

Project Officers View