Jal Jeevan Mission- 2023-24- Venganoor Panchayath- Providing Functional Household Tap Connections to remaining all households and allied works for full coverage- Phase III (Package 2)

Project Jal Jeevan Mission- 2023-24- Venganoor Panchayath- Providing Functional Household Tap Connections to remaining all households and allied works for full coverage- Phase III (Package 2)
Project Code TVMJJM022212734
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission- 2023-24- Venganoor Panchayath- Providing Functional Household Tap Connections to remaining all households and allied works for full coverage- Phase III (Package 2)
Status Completed
District Thiruvananthapuram
Executing Office Kanjiramkulam WS Sub Dn
AS Amount (Rs) 107900000
AS Number 134/2022/WRD
TS Amount (Rs) 78700000
TS Number 10120/2022-2023
Total Bill Submitted (Rs) 1
Total Bill Paid (Rs) 1
Population Benefitted 3000
Capacity in MLD 0.30
Actual Project Completion Date 31 Jan 2024
Coverage This work is including in Venganoor panchayath area.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission- 2023-24- Venganoor Panchayath- Providing Functional Household Tap Connections to remaining all households and allied works for full coverage- Phase III (Package 2) Aralummoodu WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Apr 2024 325 FHTCs are given out of 2791 & final bill submitted Aralumoodu AE
23 Apr 2024 325 FHTCs are given out of 2791 Aralumoodu AE
19 Apr 2024 325 FHTCs are given out of 2791 Aralumoodu AE
12 Apr 2024 325 FHTCs are given out of 2791 Aralumoodu AE
06 Apr 2024 325 FHTCs are given out of 2791 Aralumoodu AE

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
06 Feb 2023 Pending Pending Road Cut Related Risk Kattukulam Venniyoor road cross cutting No comments available. Pending

Duration & Sanction dates

Date of start of Project 16/09/2022
Scheduled date of Completion of the Project 15 Apr 2023
Expected date of Completion 31/01/2024

Processing Dates

AS Date 23 Feb 2022
TS Date 14 Jul 2022

Other details

Project Officers View