Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Replacement of damaged 300AC pipe with 300mm DI from Ambalaparambu to Valiyapara Kothamangalam municipality 1000m Reach II(distribution main)-Road restoration

Project Replacement of damaged 300AC pipe with 300mm DI from Ambalaparambu to Valiyapara Kothamangalam municipality 1000m Reach II(distribution main)-Road restoration
Project Code EKMKIIFB0119519P2
Type Package
Main Project WRD005-126- UWSS to Kothamangalam- Replacement of damaged 300 AC pipe with 300 mm DI from Ambalaparambu to Valiyapara Kothamangalam Municipality 1000 m Reach II (distribution main) Supplying & Laying 300mm DI K9 pipe& road restoration
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Restoring the damaged road surface
Status Completed
District Ernakulam
Executing Office Piravam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 7299000
TS Number TS/2019-2020/2019/8991
Technical specification Restoring the damaged road surface

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/01/2020
Scheduled date of Completion as per agreement 30 Sep 2020
Expected date of Completion 30/09/2020

Processing Dates

TS Date 18 Sep 2019
Estimate Approval 22 Sep 2019
NIT Approval 22 Sep 2019
Tender Closing 03 Oct 2019
Technichal Pre-Qualification 09 Oct 2019
Price bid opening 09 Oct 2019

Approval Dates

Workorder Date 31 Dec 2019
NA 10 Jan 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kattappana Project Dn EE
Date: 16/05/2023

Work has started | 0% Completed

Even after issuing letter to the contractor for commencement of this work from this office and higher office the contractor has failed to initiate the work.Hence the work may be terminated and arranged in risk and cost of the contract.

Kattappana Project Dn EE
Date: 12/05/2023

Work has started | 0% Completed

Even after issuing letter to the contractor for commencement of this work from this office and higher office the contractor has failed to initiate the work.Hence the work may be terminated and arranged in risk and cost of the contract.