- State plan 18-19 :Renovation of 7MLD WTP...
State plan 18-19 :Renovation of 7MLD WTP at Mangadikunnu including clear water chamber maintenance and allied civil works
Project |
State plan 18-19 :Renovation of 7MLD WTP at Mangadikunnu including clear water chamber maintenance and allied civil works |
Project Code |
TCRGOK08185940 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Renovation of 7MLD WTP at Mangadikunnu including clear water chamber maintenance and allied civil works |
Status |
Completed |
District |
Thrissur |
Executing Office |
Irinjalakkuda PH Sub Dn |
AS Amount (Rs) |
700000
|
AS Number |
G.O.(Rt) No.615/2018/WRD |
TS Amount (Rs) |
700000 |
TS Number |
TS/2018-2019/2018/12144 |
Total Bill Submitted (Rs) |
635129 |
Total Bill Paid (Rs) |
635129 |
Population Benefitted |
|
Capacity in MLD |
7.00 |
Actual Project Completion Date |
12 Jul 2019 |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
Renovation of 7MLD WTP at Mangadikunnu including clear water chamber maintenance and allied civil works |
Ollur Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 Jun 2021 |
Work has been completed on 12-7-2019 and FCC paid |
Irinjalakkuda PH Dn EE |
|
25 Jan 2021 |
FCC paid |
Irinjalakkuda PH Dn EE |
|
25 Jan 2021 |
work completed and bill submitted to division on 18.10.2019 |
Irinjalakkuda PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
04/02/2019 |
Scheduled date of Completion of the Project |
23 Mar 2019 |
Expected date of Completion |
12/07/2019 |
Processing Dates
AS Date |
20 Aug 2018 |
TS Date |
28 Oct 2018 |