Deposit work-Thiruvantahapuram Corporation--Project No SO548/22-Providing Water Connection to water scarcity at areas in Kammattom Lane near Excise Office, General Hospital using 63mm dia PVC 10kg/cm2 pipe through DMO compound in Vanchiyoor ward.

Project Deposit work-Thiruvantahapuram Corporation--Project No SO548/22-Providing Water Connection to water scarcity at areas in Kammattom Lane near Excise Office, General Hospital using 63mm dia PVC 10kg/cm2 pipe through DMO compound in Vanchiyoor ward.
Project Code TVMDEPO032210737
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work-Thiruvantahapuram Corporation--Project No SO548/22-Providing Water Connection to water scarcity at areas in Kammattom Lane near Excise Office, General Hospital using 63mm dia PVC 10kg/cm2 pipe through DMO compound in Vanchiyoor ward.
Status Completed
District Thiruvananthapuram
Executing Office Pattoor Sn(Maintenance)
AS Amount (Rs) 153000
AS Number J4/548/21
TS Amount (Rs) 153000
TS Number 23874/2021-2022
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage Deposit work-Thiruvantahapuram Corporation--Project No SO548/22-Providing Water Connection to water scarcity at areas in Kammattom Lane near Excise Office, General Hospital using 63mm dia PVC 10kg/cm2 pipe through DMO compound in Vanchiyoor ward.

Packages

No. Project Name Location View
1 Deposit work of TVPM corporation- project no- SO548/22-Providing water connection to water scarcity areas in Kammattom lane near excise office, General Hospital using 63mm dia PVC 10kg/cm2 pipe(100)through DMO compoung in Vanchiyoor ward Pattoor Sn(Maintenance)

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Sep 2022 Restoration of exposed pipe portion remaining Pattoor WW Sn AE
24 Aug 2022 Almost completed, concreting to be done. TVM Central Sub Dn - AEE
18 Aug 2022 temporary restoration pending Pattoor WW Sn AE
10 Aug 2022 temporary restoration pending Pattoor WW Sn AE
03 Aug 2022 Main line laying completed. Pattoor WW Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 25/05/2022
Scheduled date of Completion of the Project 24 Jun 2022
Expected date of Completion 24/06/2022

Processing Dates

AS Date 24 Mar 2022
TS Date 25 Mar 2022

Other details

Project Officers View