Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of pumping stations under PH Division, Irinjalakuda

Project Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of pumping stations under PH Division, Irinjalakuda
Project Code TCRRKI042211408
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of pumping stations under PH Division, Irinjalakuda
Status Completed
District Thrissur
Executing Office Irinjalakkuda PH Dn
AS Amount (Rs) 6600000
AS Number 6296/AE1(OPERATIONS)/2022/KWA
TS Amount (Rs) 750000
TS Number 9076/2022-2023
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 50000
Capacity in MLD 6.90
Actual Project Completion Date 06 May 2023
Coverage 100%

Packages

No. Project Name Location View
1 Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of pumping stations under PH Section No.II Chalakudy Chalakkudy PH Sn II
2 Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of pumping stations under P H Section, Ollur Ollur Sn
3 Automation of Vertical Turbine pumps in Kerala Water Authority- Implementation of Phase 1 (Stage2), part under Rebuild Kerala Initiative - Supply, installation, trial run and commissioning of Control Module for remote operation of pumping stations under WSP Section no.I Chalakudy Chalakkudy PH Sn
4 REBUILD-Automation of Vertical Turbine Pumps in KWA - Supply, Installisation, trial run and commissioning of Control Module for remote operation of pumping stations--CWSS to Nattika Firka - Automation of Vertical Turbine Pumps at Illikkal RW Pump House Mathilakam PH Sn
5 REBUILD-Automation of VT pump set under Cherpu section-RKI - Supply, Installation, trail run and commissioning of Contol Module for remote operation of VT pumping stations under Cherpu section Cherpu PH Sn
6 REBUILD- IWSS- Supply, Installation, trial run and commissioning of Control Module for remote operation of pumping stations- Raw water pump house Karuvannur- under P H Section, Irinjalakuda Irinjalakkuda PH Sn
7 REBUILD- KPCTA Karalam, Padiyur- Supply, Installation, trial run and commissioning of Control Module for remote operation of pumping stations- Raw water pump house at Illikkal - Under P H Section, Irinjalakuda Irinjalakkuda PH Sn
8 REBUILD- RDWSS to Kattoor Padiyur Poomangalam and adjoining villages- Supply, Installation, trial run and commissioning of Control Module for remote operation of pumping stations- Raw water pump house at Illikkal - Under P H Section, Irinjalakuda Irinjalakkuda PH Sn
9 REBUILD- RWSS to Thottippal- Supply, Installation, trial run and commissioning of Control Module for remote operation of pumping stations- Raw water pump house at Thottippal- under P H Section, Irinjalakuda Irinjalakkuda PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 work completed on 06/05/2023. bill Submitted-20/06/2023 Mathilakam AE
02 May 2024 work completed on 06/05/2023. bill Submitted-20/06/2023 Mathilakam AE
23 Apr 2024 work completed on 06/05/2023. bill Submitted-20/06/2023 Ollur AE
17 Apr 2024 work completed on 06/05/2023. bill Submitted-20/06/2023 Mathilakam AE
27 Mar 2024 work completed on 06/05/2023. bill Submitted-20/06/2023 Mathilakam AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 19/04/2022
Scheduled date of Completion of the Project 30 Sep 2022
Expected date of Completion 30/04/2023

Processing Dates

AS Date 19 Apr 2022
TS Date 02 Jul 2022

Other details

Project Officers View