| Project | DRW 2022 -RWSS to Muttil Zone I - Kumblad - Urgent Interconnection at Chenamkolly Canal Road in Muttil Grama Panchyath |
|---|---|
| Project Code | WYDGOK03229646P1 |
| Type | Package |
| Main Project | DRW 2022 - Urgent Interconnection works |
| Funding Agency | GOK |
| Category | DRW |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | DRW 2022 -RWSS to Muttil Zone I - Kumblad - Urgent Interconnection at Chenamkolly Canal Road in Muttil Grama Panchyath |
| Status | On-going |
| District | Wayanad |
| Executing Office | Kalpetta PH Sn 1 |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 550000 |
| TS Number | 9567/2022-23 |
| Technical specification | Inter connection work |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 30/03/2022 |
|---|---|
| Scheduled date of Completion as per agreement | 30 Nov 2022 |
| Expected date of Completion | 30/11/2022 |
| TS Date | 08 Jul 2022 |
|---|---|
| Estimate Approval | 08 Jul 2022 |
| NIT Approval | 22 Jul 2022 |
| Tender Closing | 29 Jul 2022 |
| Technichal Pre-Qualification | 05 Jan 2022 |
| Price bid opening | 10 Jan 2022 |
| Workorder Date | 30 Mar 2022 |
|---|---|
| NA | 30 Mar 2022 |
| Sulthan Bathery PH Dn EE |
| Date: 21/10/2023 |
Work has been completed | 100% Completed
Work completed and bill submitted.
| Sulthan Bathery PH Dn EE |
| Date: 05/10/2023 |
Work has been completed | 100% Completed
Work completed and bill submitted.