AMRUT-2015-16-Rehabiltation of Thrissur Corporation WSS to Koorkancherry Zone (AS- 3.71 Cr)
Project |
AMRUT-2015-16-Rehabiltation of Thrissur Corporation WSS to Koorkancherry Zone (AS- 3.71 Cr) |
Project Code |
TCRAMRUT0217524 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT-2015-16-Rehabiltation of Thrissur Corporation WSS to Koorkancherry Zone - Supply and laying seperate branched gravity main of 400mm DI K9 and supply erection and commissioning of 65HP centrifugal motor pumpset for replacing of existing old pumpsets - 2nos at Koorkancherry sump and allied works.
1. Transmission main -400mmDI -3241m,
2.Replacement of pipes-700mm DI pipe- 60m.
3. pumpset - 2 nos,
4. Chlorinator ( Tonner 1 No , 100 KG Cylinder 2nos |
Status |
Completed |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
37131035
|
AS Number |
G.O.(Rt)No.1390/2020/LSGD |
TS Amount (Rs) |
37131035 |
TS Number |
AMRUT/TEC/NR/2/2017 |
Total Bill Submitted (Rs) |
36958605 |
Total Bill Paid (Rs) |
36958605 |
Population Benefitted |
10000 |
Capacity in MLD |
0.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
This project is mainly intended to improve the existing water supply to Koorkenchery zone (Divisions 31,32,33,34,39,40,41 & 42 of Thrissur corporation) |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-2015-16-Rehabiltation of Thrissur Corporation WSS to Koorkancherry Zone |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jan 2022 |
Work completed and commissioned on 31/08/2019. |
Nattika Proj Dn AEE |
|
13 Feb 2021 |
Work completed and commissioned on 31/08/2019. |
Nattika Proj Dn AEE |
|
13 Sep 2020 |
Work completed and commissioned on 31/08/2019. Handed over to Water works Section No.II, KWA, Thrissur on 03/09/2020 |
Nattika Project Dn AE 5 |
|
19 Jun 2020 |
Work completed
Final bill submitted to CMMU Thrissur. |
Nattika Project Dn AE 5 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/01/2018 |
Scheduled date of Completion of the Project |
15 Jan 2019 |
Expected date of Completion |
31/08/2019 |
Processing Dates
AS Date |
23 Feb 2017 |
TS Date |
03 May 2017 |