NABARD RIDF-XXV-CWSS TO VITHURA THOLICODE-Phase II

Project NABARD RIDF-XXV-CWSS TO VITHURA THOLICODE-Phase II
Project Code TVMNABARD1119626
Type Main project
Funding Agency NABARD
Category NABARD
Type of scheme Water Supply
Scheme
Description Supplying,Laying,Testing and Commissioning of 200mm and 150mm DI K9 CWPM to proposed OHSR at Kundalamkuzhy . Supplying,Laying,Testing and Commissioning of 150mm DI K9 CWGM to proposed SUMP at Meletholicodu Supplying,Laying,Testing and Commissioning of 200mm DI K9 CWPM to proposed OHSR at Pachamala. Construction of 1.00 LL OHSR at Kundalamkuzhy,Construction of 1.67 LL OHSR at Pachamala, Construction of 2.00 LL SUMP and PUMP HOUSE at Meletholicodu. Supplying,Laying,Testing and Commissioning of Distribution Network of Zone-II,Supplying,Laying,Testing and Commissioning of Distribution Network of Zone-IV, Supply,Erection,Testing and Commissioning of Clear Water Pump Set(CF) to proposed OHSR at Kundalamkuzhy, Supply,Erection,Testing and Commissioning of Clear Water Pump Set(CF) to proposed OHSR at Pachamala. Supplying, Laying, Testing and Commissioning of Distribution Network of Zone-III
Status On-going
District Thiruvananthapuram
Executing Office Trivandrum Project Dn
AS Amount (Rs) 315000000
AS Number G.O.(Rt)No.800/2019/WRD
TS Amount (Rs) 253600000
TS Number TS/2020-2021/2020/2242; TS/2020-2021/2020/2243; TS/2020-2021/2020/2246 ; TS/2020-21/2020/2249
Total Bill Submitted (Rs) 87987837
Total Bill Paid (Rs) 43800000
Population Benefitted 100881
Capacity in MLD 5.80
Actual Project Completion Date 27 Apr 2022
Coverage Design Population for the entire scheme in 2031 is 100881
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 CWSS TO VITHURA THOLICODE-Phase II Package I Trivandrum Project Dn
2 CWSS TO VITHURA THOLICODE-Phase II Package II Trivandrum Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Mar 2024 CWSS TO VITHURA THOLICODE-Phase II Package I (90% completed) Interconection work in RICK road, 300m gap in pwd road, KSEB Power allocation ( With transformer) pending CWSS TO VITHURA THOLICODE-Phase II Package II (95% completed) Around 3.8 km pipelaying work pending ( Rick and PWD road) Thiruvananthapuram Project AE4
02 Feb 2024 CWSS TO VITHURA THOLICODE-Phase II Package I (90% completed) Interconection work in RICK road, 300m gap in pwd road, KSEB Power allocation ( With transformer) pending CWSS TO VITHURA THOLICODE-Phase II Package II (95% completed) Around 4 km pipelaying work pending ( Rick and PWD road) Thiruvananthapuram Project AE4
26 Oct 2023 Package I (90% Completed): 1 Contractor has supplied DI and PVC pipes. (2) 150mm DI K9 clear water gravity main from eruthalamool jn towards thottumukku tank started and total pipe laid for a length of 3657m. (3)150mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 2272m. (4) Distribution from kundalamkuzhy tank started and total pipe laid for a length of 3681m (5) 200mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 255.3m 6) Distribution from Pachamala tank started and total pipe laid for a length of 9169.7m (7) 200mm DI pumping main from pachamala tank start laying and laid for a length of 1632.7m. Total pipe laid for a length of 20.67Km out of 25.83Km. (8) Civil structure of 1.00 LL OHSR at Kundalamkuzhy completed. (9)Civil structure of 2.00 LL Sump cum pumphouse at Meletholicodu completed. (10)Civil structure of 1.67 LL OHSR at Pachamala completed Package II (86% Completed): 1 Contractor has supplied DI and PVC pipes. (2) Distribution from thottumukku tank is in progress and total pipe laid for a length of 39.47Km out of 48.47Km. Thiruvananthapuram Project AE4
30 Jan 2023 Package I (87% Completed): 1 Contractor has supplied DI and PVC pipes. (2) 150mm DI K9 clear water gravity main from eruthalamool jn towards thottumukku tank started and total pipe laid for a length of 3657m. (3)150mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 2272m. (4) Distribution from kundalamkuzhy tank started and total pipe laid for a length of 3681m (5) 200mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 255.3m 6) Distribution from Pachamala tank started and total pipe laid for a length of 9169.7m (7) 200mm DI pumping main from pachamala tank start laying and laid for a length of 1632.7m. Total pipe laid for a length of 20.67Km out of 25.83Km. (8) Civil structure of 1.00 LL OHSR at Kundalamkuzhy completed. (9)Civil structure of 2.00 LL Sump cum pumphouse at Meletholicodu completed. (10)Civil structure of 1.67 LL OHSR at Pachamala completed Package II (85% Completed): 1 Contractor has supplied DI and PVC pipes. (2) Distribution from thottumukku tank is in progress and total pipe laid for a length of 39.47Km out of 48.47Km. (3). Road cutting sanction pending from RICK for a length of 4km from Iruthalamoola to Parandode. Demand received from Rick was submitted for payment (4) Road cutting sanction pending from PWD for a length of 2.3 km from Panacode to bridge near manoorkanam ( Road in DLP) Thiruvananthapuram Project AE4
03 Jan 2023 Package I (87% Completed): 1 Contractor has supplied DI and PVC pipes. (2) 150mm DI K9 clear water gravity main from eruthalamool jn towards thottumukku tank started and total pipe laid for a length of 3657m. (3)150mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 2272m. (4) Distribution from kundalamkuzhy tank started and total pipe laid for a length of 3681m (5) 200mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 255.3m 6) Distribution from Pachamala tank started and total pipe laid for a length of 9169.7m (7) 200mm DI pumping main from pachamala tank start laying and laid for a length of 1632.7m. Total pipe laid for a length of 20.67Km out of 25.83Km. (8) Civil structure of 1.00 LL OHSR at Kundalamkuzhy completed. (9)Civil structure of 2.00 LL Sump cum pumphouse at Meletholicodu completed. (10)Civil structure of 1.67 LL OHSR at Pachamala completed Package II (85% Completed): 1 Contractor has supplied DI and PVC pipes. (2) Distribution from thottumukku tank is in progress and total pipe laid for a length of 39.47Km out of 48.47Km. (3). Road cutting sanction pending from RICK for a length of 4km from Iruthalamoola to Parandode. Demand received from Rick was submitted for payment (4) Road cutting sanction pending from PWD for a length of 2.3 km from Panacode to bridge near manoorkanam ( Road in DLP) Thiruvananthapuram Project AE4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 22/02/2021
Scheduled date of Completion of the Project 31 Jul 2022
Expected date of Completion 30/12/2022