NABARD RIDF-XXV-CWSS TO VITHURA THOLICODE-Phase II
Project |
NABARD RIDF-XXV-CWSS TO VITHURA THOLICODE-Phase II |
Project Code |
TVMNABARD1119626 |
Type |
Main project |
Funding Agency |
NABARD |
Category |
NABARD |
Type of scheme |
Water Supply |
Scheme |
|
Description |
Supplying,Laying,Testing and Commissioning of 200mm and 150mm DI K9 CWPM to proposed OHSR at Kundalamkuzhy . Supplying,Laying,Testing and Commissioning of 150mm DI K9 CWGM to proposed SUMP at Meletholicodu Supplying,Laying,Testing and Commissioning of 200mm DI K9 CWPM to proposed OHSR at Pachamala. Construction of 1.00 LL OHSR at Kundalamkuzhy,Construction of 1.67 LL OHSR at Pachamala, Construction of 2.00 LL SUMP and PUMP HOUSE at Meletholicodu. Supplying,Laying,Testing and Commissioning of Distribution Network of Zone-II,Supplying,Laying,Testing and Commissioning of Distribution Network of Zone-IV, Supply,Erection,Testing and Commissioning of Clear Water Pump Set(CF) to proposed OHSR at Kundalamkuzhy, Supply,Erection,Testing and Commissioning of Clear Water Pump Set(CF) to proposed OHSR at Pachamala. Supplying, Laying, Testing and Commissioning of Distribution Network of Zone-III |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Trivandrum Project Dn |
AS Amount (Rs) |
315000000
|
AS Number |
G.O.(Rt)No.800/2019/WRD |
TS Amount (Rs) |
253600000 |
TS Number |
TS/2020-2021/2020/2242; TS/2020-2021/2020/2243; TS/2020-2021/2020/2246 ; TS/2020-21/2020/2249 |
Total Bill Submitted (Rs) |
87987837 |
Total Bill Paid (Rs) |
43800000 |
Population Benefitted |
100881 |
Capacity in MLD |
5.80 |
Actual Project Completion Date |
27 Apr 2022 |
Coverage |
Design Population for the entire scheme in 2031 is 100881 |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
CWSS TO VITHURA THOLICODE-Phase II Package I |
Trivandrum Project Dn |
|
2 |
CWSS TO VITHURA THOLICODE-Phase II Package II |
Trivandrum Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
03 Mar 2024 |
CWSS TO VITHURA THOLICODE-Phase II Package I (90% completed) Interconection work in RICK road, 300m gap in pwd road, KSEB Power allocation ( With transformer) pending CWSS TO VITHURA THOLICODE-Phase II Package II (95% completed) Around 3.8 km pipelaying work pending ( Rick and PWD road) |
Thiruvananthapuram Project AE4 |
|
02 Feb 2024 |
CWSS TO VITHURA THOLICODE-Phase II Package I (90% completed) Interconection work in RICK road, 300m gap in pwd road, KSEB Power allocation ( With transformer) pending
CWSS TO VITHURA THOLICODE-Phase II Package II (95% completed) Around 4 km pipelaying work pending ( Rick and PWD road) |
Thiruvananthapuram Project AE4 |
|
26 Oct 2023 |
Package I (90% Completed): 1 Contractor has supplied DI and PVC pipes. (2) 150mm DI K9 clear water gravity main from eruthalamool jn towards thottumukku tank started and total pipe laid for a length of 3657m. (3)150mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 2272m. (4) Distribution from kundalamkuzhy tank started and total pipe laid for a length of 3681m (5) 200mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 255.3m 6) Distribution from Pachamala tank started and total pipe laid for a length of 9169.7m (7) 200mm DI pumping main from pachamala tank start laying and laid for a length of 1632.7m. Total pipe laid for a length of 20.67Km out of 25.83Km. (8) Civil structure of 1.00 LL OHSR at Kundalamkuzhy completed. (9)Civil structure of 2.00 LL Sump cum pumphouse at Meletholicodu completed. (10)Civil structure of 1.67 LL OHSR at Pachamala completed Package II (86% Completed): 1 Contractor has supplied DI and PVC pipes. (2) Distribution from thottumukku tank is in progress and total pipe laid for a length of 39.47Km out of 48.47Km. |
Thiruvananthapuram Project AE4 |
|
30 Jan 2023 |
Package I (87% Completed): 1 Contractor has supplied DI and PVC pipes. (2) 150mm DI K9 clear water gravity main from eruthalamool jn towards thottumukku tank started and total pipe laid for a length of 3657m. (3)150mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 2272m. (4) Distribution from kundalamkuzhy tank started and total pipe laid for a length of 3681m (5) 200mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 255.3m 6) Distribution from Pachamala tank started and total pipe laid for a length of 9169.7m (7) 200mm DI pumping main from pachamala tank start laying and laid for a length of 1632.7m. Total pipe laid for a length of 20.67Km out of 25.83Km. (8) Civil structure of 1.00 LL OHSR at Kundalamkuzhy completed. (9)Civil structure of 2.00 LL Sump cum pumphouse at Meletholicodu completed. (10)Civil structure of 1.67 LL OHSR at Pachamala completed Package II (85% Completed): 1 Contractor has supplied DI and PVC pipes. (2) Distribution from thottumukku tank is in progress and total pipe laid for a length of 39.47Km out of 48.47Km. (3). Road cutting sanction pending from RICK for a length of 4km from Iruthalamoola to Parandode. Demand received from Rick was submitted for payment (4) Road cutting sanction pending from PWD for a length of 2.3 km from Panacode to bridge near manoorkanam ( Road in DLP) |
Thiruvananthapuram Project AE4 |
|
03 Jan 2023 |
Package I (87% Completed): 1 Contractor has supplied DI and PVC pipes. (2) 150mm DI K9 clear water gravity main from eruthalamool jn towards thottumukku tank started and total pipe laid for a length of 3657m. (3)150mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 2272m. (4) Distribution from kundalamkuzhy tank started and total pipe laid for a length of 3681m (5) 200mm DI K9 clear water pumping main from WTP towards kundalamkuzhy tank started and total pipe laid for a length of 255.3m 6) Distribution from Pachamala tank started and total pipe laid for a length of 9169.7m (7) 200mm DI pumping main from pachamala tank start laying and laid for a length of 1632.7m. Total pipe laid for a length of 20.67Km out of 25.83Km. (8) Civil structure of 1.00 LL OHSR at Kundalamkuzhy completed. (9)Civil structure of 2.00 LL Sump cum pumphouse at Meletholicodu completed. (10)Civil structure of 1.67 LL OHSR at Pachamala completed Package II (85% Completed): 1 Contractor has supplied DI and PVC pipes. (2) Distribution from thottumukku tank is in progress and total pipe laid for a length of 39.47Km out of 48.47Km. (3). Road cutting sanction pending from RICK for a length of 4km from Iruthalamoola to Parandode. Demand received from Rick was submitted for payment (4) Road cutting sanction pending from PWD for a length of 2.3 km from Panacode to bridge near manoorkanam ( Road in DLP) |
Thiruvananthapuram Project AE4 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/02/2021 |
Scheduled date of Completion of the Project |
31 Jul 2022 |
Expected date of Completion |
30/12/2022 |
Processing Dates
AS Date |
08 Nov 2019 |
TS Date |
21 May 2020 |