- Home
- Deposit work :- Extension of 50 mm pvc p...
Deposit work :- Extension of 50 mm pvc pipe line along to Uchakkvu -aanappara at kodiyathoor panchayath.
Project |
Deposit work :- Extension of 50 mm pvc pipe line along to Uchakkvu -aanappara at kodiyathoor panchayath. |
Project Code |
CLTDEPO05209229 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work :- Extension of 50 mm pvc pipe line along to Uchakkvu -Aanappara at Kodiyathoor panchayath. |
Status |
Completed |
District |
Kozhikkode |
Executing Office |
Koduvally Sn |
AS Amount (Rs) |
145000
|
AS Number |
U000000788156440 |
TS Amount (Rs) |
145000 |
TS Number |
No. 14729/2021-2022 |
Total Bill Submitted (Rs) |
126649 |
Total Bill Paid (Rs) |
126649 |
Population Benefitted |
14 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Work Completed |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work :- Extension of 50 mm pvc pipe line along to Uchakkvu -aanappara at kodiyathoor panchayath. |
Koduvally Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Mar 2022 |
ALL WORKS COMPLETED. |
Kodually W S section - AE |
|
14 Mar 2022 |
work started on 13-01-2022 and completed and commissioned on 20-01-2022 |
Kozhikode PH Dn EE |
|
11 Mar 2022 |
work started on 13-01-2022 and completed and commissioned on 20-01-2022 |
Kozhikode PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
10/01/2022 |
Scheduled date of Completion of the Project |
21 Mar 2022 |
Expected date of Completion |
21/03/2022 |
Processing Dates
AS Date |
19 May 2020 |
TS Date |
04 Dec 2021 |