State Plan 2021-22 TSS- E Block Zone II - Laying 630mm dia HDPE pipe sewer main from Edapazhanji to Chithra nagar first reach- Ch 1841 m to 2133 m
Project |
State Plan 2021-22 TSS- E Block Zone II - Laying 630mm dia HDPE pipe sewer main from Edapazhanji to Chithra nagar first reach- Ch 1841 m to 2133 m |
Project Code |
TVMGOK05217499 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
State Plan 2021-22 TSS- E Block Zone II - Laying 630mm dia HDPE pipe sewer main from Edapazhanji to Chithra nagar first reach- Ch 1841 m to 2133 m |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Plamoodu project Sn |
AS Amount (Rs) |
21500000
|
AS Number |
PIU1/SP/59/2022-23 |
TS Amount (Rs) |
21300000 |
TS Number |
9845/2022-2023 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
6000 |
Capacity in MLD |
0.01 |
Actual Project Completion Date |
12 Apr 2023 |
Coverage |
State Plan 2021-22 TSS- E Block Zone II - Laying 630mm dia HDPE pipe sewer main from Edapazhanji to Chithra nagar first reach- Ch 1841 m to 2133 m |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan 2021-22 TSS- E Block Zone II - Laying 630mm dia HDPE pipe sewer main from Edapazhanji to Chithra nagar first reach- Ch 1841 m to 2133 m |
Plamoodu project Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 May 2024 |
Contractor has stopped the work since 21.04.2024. Even after repeated reminders, the contractor has not restarted the work. |
Plamoodu Sewerage Project Sn AE |
|
19 Apr 2024 |
Pipe joint work is in Progress. |
Plamoodu Sewerage Project Sn AE |
|
08 Apr 2024 |
Contractor was given a reminder letter directing to complete the work immediately |
Plamoodu Sewerage Project Sn AE |
|
31 Mar 2024 |
Contractor was given a reminder letter directing to complete the work immediately |
Plamoodu Sewerage Project Sn AE |
|
20 Mar 2024 |
Contractor was given a reminder letter directing to complete the work immediately |
Plamoodu Sewerage Project Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
13/10/2022 |
Scheduled date of Completion of the Project |
12 Apr 2023 |
Expected date of Completion |
30/09/2023 |
Processing Dates
AS Date |
27 Jun 2022 |
TS Date |
12 Jul 2022 |