DEPOSIT-Alappuzha Jilla Panchayat- Chennithala Division.-Deposit work-Alappuzha Jilla Panchayat- Chennithala Division - RWSS to Chettikulangara-Extension of pipe line at various places in ward XIII of Chettikulangara Panchayat
Project |
DEPOSIT-Alappuzha Jilla Panchayat- Chennithala Division.-Deposit work-Alappuzha Jilla Panchayat- Chennithala Division - RWSS to Chettikulangara-Extension of pipe line at various places in ward XIII of Chettikulangara Panchayat |
Project Code |
ALPDEPO112214381 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Extension of pipe line at various places in ward XIII of Chettikulangara Panchayat |
Status |
Completed |
District |
Alappuzha |
Executing Office |
Alappuzha PH Dn |
AS Amount (Rs) |
2700000
|
AS Number |
HL-2450(4)/22 |
TS Amount (Rs) |
2580000 |
TS Number |
WRD/KWA-CEP/EST_TS/136/2022_26_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
500 |
Capacity in MLD |
0.10 |
Actual Project Completion Date |
05 Oct 2023 |
Coverage |
Ward 13 |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-Alappuzha Jilla Panchayat- Chennithala Division.-Deposit work-Alappuzha Jilla Panchayat- Chennithala Division - RWSS to Chettikulangara-Extension of pipe line at various places in ward XIII of Chettikulangara Panchayat |
Mavelikkara WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Oct 2023 |
Work completed |
Mavelikkara PH Sn AE |
|
03 Oct 2023 |
Awaiting Road Cutting permission from PWD |
Mavelikkara PH Sn AE |
|
27 Sep 2023 |
Awaiting Road Cutting permission from PWD |
Mavelikkara PH Sn AE |
|
14 Sep 2023 |
Awaiting Road Cutting permission from PWD |
Mavelikkara PH Sn AE |
|
07 Sep 2023 |
Work in progress |
Mavelikkara PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
26/06/2023 |
Scheduled date of Completion of the Project |
12 Dec 2023 |
Expected date of Completion |
31/10/2023 |
Processing Dates
AS Date |
04 Nov 2022 |
TS Date |
06 Jan 2023 |