DEPOSIT-Kollam corporation Deposit work - Supply, Erecting and commissioning of pump set at Vettuvila Tube well scheme and construction of pump houseand connected works. -General Civil Work

Project DEPOSIT-Kollam corporation Deposit work - Supply, Erecting and commissioning of pump set at Vettuvila Tube well scheme and construction of pump houseand connected works. -General Civil Work
Project Code KLMDEPO122315524P1
Type Package
Main Project DEPOSIT-Kollam corporation Deposit work - Supply, Erecting and commissioning of pump set at Vettuvila Tube well scheme and construction of pump houseand connected works. -General Civil Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Kollam corporation Deposit work - Supply, Erecting and commissioning of pump set at Vettuvila Tube well scheme and construction of pump houseand connected works. -General Civil Work
Status On-going
District Kollam
Executing Office Kollam WS Sn 2
Agreement Number
Agreement Date
TS Amount (Rs) 540000
TS Number WRD/KWA-CE(SR)/EST_TS/5941/2023_5_1_1
Technical specification DEPOSIT-Kollam corporation Deposit work - Supply, Erecting and commissioning of pump set at Vettuvila Tube well scheme and construction of pump houseand connected works. -General Civil Work

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 22/12/2023
Scheduled date of Completion as per agreement 02 Mar 2024
Expected date of Completion 02/03/2024

Processing Dates

TS Date 29 Dec 2023
Estimate Approval 22 Dec 2023
NIT Approval 22 Dec 2023
Tender Closing 10 Jan 2024
Technichal Pre-Qualification 10 Jan 2024
Price bid opening 11 Jan 2024

Approval Dates

Workorder Date 20 Jan 2024
NA 03 Feb 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam WS Sn 2 - AE
Date: 01/04/2024

Work has been completed | 100% Completed

KSEB connection got on 27/3/24 and pump erection and interconnection works completed on 30/3/24.

Kollam WS Sn 2 - AE
Date: 25/03/2024

Work in progress | 70% Completed

KSEB connection not get till date, follow up action is ongoing, .