Jal Jeevan Mission - 2020-21 -Providing FHTCs in Kodumbu and Polpully Panchayat for full coverage including Survey and Investigation, Design of network, supplying and Laying of CWPM, Maintenance on EPCM basis, Supply and Erection of CW pump sets, up-gradation of transformer and construction of 7.00 LL OHSRs each at Kodumbu and Polpully.

Project Jal Jeevan Mission - 2020-21 -Providing FHTCs in Kodumbu and Polpully Panchayat for full coverage including Survey and Investigation, Design of network, supplying and Laying of CWPM, Maintenance on EPCM basis, Supply and Erection of CW pump sets, up-gradation of transformer and construction of 7.00 LL OHSRs each at Kodumbu and Polpully.
Project Code PKDJJM12207875
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission - 2020-21 -Providing FHTCs in Kodumbu and Polpully Panchayat for full coverage including Survey and Investigation, Design of network, supplying and Laying of CWPM, Maintenance on EPCM basis, Supply and Erection of CW pump sets, up-gradation of transformer and construction of 7.00 LL OHSRs each at Kodumbu and Polpully.
Status On-going
District Palakkad
Executing Office Chittur Project Dn
AS Amount (Rs) 489941000
AS Number GO(Rt)No.777/2020/WRD
TS Amount (Rs) 385904000
TS Number polpully-TS/2020-2021/2020/24869 dtd 29.01.2021 kodumbu-TS/2021-2022/2020/23243/dtd 16.04.2021
Total Bill Submitted (Rs) 155522918
Total Bill Paid (Rs) 155522918
Population Benefitted 40328
Capacity in MLD 8.00
Actual Project Completion Date 25 Apr 2022
Coverage kodumbu ,polpully

Packages

No. Project Name Location View
1 Jal Jeevan Mission - 2020-21 -Providing FHTCs in Kodumbu and Polpully Panchayat for full coverage including Survey and Investigation, Design of network, supplying and Laying of CWPM, Maintenance on EPCM basis, Supply and Erection of CW pump sets, up-gradation of transformer and construction of 7.00 LL OHSRs each at Kodumbu and Polpully. Project Division Chittur

Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Apr 2024 Work in progress | 96% Completed | 23/04/2024 PWD ROAD RESTORATION WORK IN PROGRESS kodumbu panchayath-GI PIPE work in progress. Total supply-100km ,total laid- 97.766km laid/out of 98 km polpully panchayath- 45.316 km laid, kodumbu panchayath- 48.830km laid, FHTC-Total 3711/9079 nos provided , Polpully panchayath, 1). 350mmDI- 42.50M 2).300mm DI-1236 M 3).250mm DI-4507.80M 4.) 200mm DI -1425 M 5).110mm6kg - 1554 m 6)100mm GI - 60M ,50MM GI-30M 7).90MM 6KG-21731.m 8).80MM GI-250M 9).140mm 6kg-2235m, 10)160mm pvc-1218m 11)125mm GI-30m 12)100 mm GI-22M 13)150mm GI pipe-162m 14) 140mm 8kg-174m 15) FHTC-938/out of 2870 nos, 16)32mm GI-396M KODUMBU Panchayath 1).90mm 6kg-41966m 2)350mmDI-493.50M 3)160MM PVC-3652M 4)250 mm DI-3608.50M 5) 150mm GI pipe-180m 6) 80mm GI pipe-198m 7)32mm GI-1074M 8) 50 MM GI-228 m 75mm pvc pipe-780 m laid 7)FHTC-2823/6209 Nos 1).Kodumbu 3 MLD WTP –Painting work completed 2).Polpully and kodumbu 7LL OHSR – Painting work completed Chittur Project Dn - EE
01 Mar 2024 Work in progress | 96% Completed | 01/03/2024 PWD ROAD RESTORATION WORK IN PROGRESS kodumbu panchayath-GI PIPE work in progress. Total supply-100km ,total laid- 97.766km laid/out of 98 km polpully panchayath- 45.316 km laid, kodumbu panchayath- 48.830km laid, FHTC-Total 3711/9079 nos provided , Polpully panchayath, 1). 350mmDI- 42.50M 2).300mm DI-1236 M 3).250mm DI-4507.80M 4.) 200mm DI -1425 M 5).110mm6kg - 1554 m 6)100mm GI - 60M ,50MM GI-30M 7).90MM 6KG-21731.m 8).80MM GI-250M 9).140mm 6kg-2235m, 10)160mm pvc-1218m 11)125mm GI-30m 12)100 mm GI-22M 13)150mm GI pipe-162m 14) 140mm 8kg-174m 15) FHTC-938/out of 2870 nos, 16)32mm GI-396M KODUMBU Panchayath 1).90mm 6kg-41966m 2)350mmDI-493.50M 3)160MM PVC-3652M 4)250 mm DI-3608.50M 5) 150mm GI pipe-180m 6) 80mm GI pipe-198m 7)32mm GI-1074M 8) 50 MM GI-228 m 75mm pvc pipe-780 m laid 7)FHTC-2823/6209 Nos 1).Kodumbu 3 MLD WTP –Painting work completed 2).Polpully and kodumbu 7LL OHSR – Painting work complete Chittur Project Dn - EE
23 Feb 2024 WD ROAD RESTORATION WORK IN PROGRESS kodumbu panchayath-GI PIPE work in progress. Total supply-100km ,total laid- 97.766km laid/out of 98 km polpully panchayath- 45.316 km laid, kodumbu panchayath- 48.830km laid, FHTC-Total 3711/9079 nos provided , Polpully panchayath, 1). 350mmDI- 42.50M 2).300mm DI-1236 M 3).250mm DI-4507.80M 4.) 200mm DI -1425 M 5).110mm6kg - 1554 m 6)100mm GI - 60M ,50MM GI-30M 7).90MM 6KG-21731.m 8).80MM GI-250M 9).140mm 6kg-2235m, 10)160mm pvc-1218m 11)125mm GI-30m 12)100 mm GI-22M 13)150mm GI pipe-162m 14) 140mm 8kg-174m 15) FHTC-938/out of 2870 nos, 16)32mm GI-396M KODUMBU Panchayath 1).90mm 6kg-41966m 2)350mmDI-493.50M 3)160MM PVC-3652M 4)250 mm DI-3608.50M 5) 150mm GI pipe-180m 6) 80mm GI pipe-198m 7)32mm GI-1074M 8) 50 MM GI-228 m 75mm pvc pipe-780 m laid 7)FHTC-2823/6209 Nos 1).Kodumbu 3 MLD WTP –Painting work completed 2).Polpully and kodumbu 7LL OHSR – Painting work completed Chittur Project Dn - EE
15 Feb 2024 Work in progress | 96% Completed | 15/02/2024 PWD ROAD RESTORATION WORK IN PROGRESS kodumbu panchayath-GI PIPE work in progress. Total supply-100km ,total laid- 97.766km laid/out of 98 km polpully panchayath- 45.316 km laid, kodumbu panchayath- 48.830km laid, FHTC-Total 3711/9079 nos provided , Polpully panchayath, 1). 350mmDI- 42.50M 2).300mm DI-1236 M 3).250mm DI-4507.80M 4.) 200mm DI -1425 M 5).110mm6kg - 1554 m 6)100mm GI - 60M ,50MM GI-30M 7).90MM 6KG-21731.m 8).80MM GI-250M 9).140mm 6kg-2235m, 10)160mm pvc-1218m 11)125mm GI-30m 12)100 mm GI-22M 13)150mm GI pipe-162m 14) 140mm 8kg-174m 15) FHTC-938/out of 2870 nos, 16)32mm GI-396M KODUMBU Panchayath 1).90mm 6kg-41966m 2)350mmDI-493.50M 3)160MM PVC-3652M 4)250 mm DI-3608.50M 5) 150mm GI pipe-180m 6) 80mm GI pipe-198m 7)32mm GI-1074M 8) 50 MM GI-228 m 75mm pvc pipe-780 m laid 7)FHTC-2823/6209 Nos 1).Kodumbu 3 MLD WTP –Painting work completed 2).Polpully and kodumbu 7LL OHSR – Painting work completed Chittur Project Dn - EE
26 Jan 2024 Work in progress | 96% Completed | 24/01/2024 PWD ROAD RESTORATION WORK IN PROGRESS kodumbu panchayath-GI PIPE work in progress. Total supply-100km ,total laid- 97.766km laid/out of 98 km polpully panchayath- 45.316 km laid, kodumbu panchayath- 48.830km laid, FHTC-Total 3711/9079 nos provided , Polpully panchayath, 1). 350mmDI- 42.50M 2).300mm DI-1236 M 3).250mm DI-4507.80M 4.) 200mm DI -1425 M 5).110mm6kg - 1554 m 6)100mm GI - 60M ,50MM GI-30M 7).90MM 6KG-21731.m 8).80MM GI-250M 9).140mm 6kg-2235m, 10)160mm pvc-1218m 11)125mm GI-30m 12)100 mm GI-22M 13)150mm GI pipe-162m 14) 140mm 8kg-174m 15) FHTC-938/out of 2870 nos, 16)32mm GI-396M KODUMBU Panchayath 1).90mm 6kg-41966m 2)350mmDI-493.50M 3)160MM PVC-3652M 4)250 mm DI-3608.50M 5) 150mm GI pipe-180m 6) 80mm GI pipe-198m 7)32mm GI-1074M 8) 50 MM GI-228 m 75mm pvc pipe-780 m laid 7)FHTC-2823/6209 Nos 1).Kodumbu 3 MLD WTP –Painting work completed 2).Polpully and kodumbu 7LL OHSR – Painting work completed Chittur Project Dn - EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 26/04/2021
Scheduled date of Completion of the Project 25 Apr 2022
Expected date of Completion 31/12/2023

Processing Dates

AS Date 24 Dec 2020
TS Date 29 Jan 2021

Other details

Project Officers View