WSS to Pavaratty and Mullassery Panchayaths - Gravity main

Project WSS to Pavaratty and Mullassery Panchayaths - Gravity main
Project Code TCRGOK1018615
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description WSS to Pavaratty and Mullassery Panchayath in Chavakkad Thaluk – Supplying, laying, testing and commissioning 300/250/200 mm DI K9 gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam
Status On-going
District Thrissur
Executing Office Nattika Project Dn
AS Amount (Rs) 56176000
AS Number KWA/HO/W/TSR/TD/03/04/2017
TS Amount (Rs) 136000000
TS Number TS/CE/CR/KWA/17/16-17
Total Bill Submitted (Rs) 54819862
Total Bill Paid (Rs) 27970000
Population Benefitted 52081
Capacity in MLD 33.00
Actual Project Completion Date Date is not specified
Coverage Pavaratty and Mullassery
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 WSS to Pavaratty and mullassery panchayath s - Gravity main Nattika Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Mar 2023 Laying work of 300mm DIK9 pipe is completed from Polemasterpadi to Pavaratty Jn.and 1380m length pipe laid. Total laying length of 300 mm is 6.60 km and total laying length of 250mm DIK9 is 2.30 km .Out of 13.8 km,total 8.90km laying completed .For the completion of work, it is necessary to obtain railway crossing permission. Application ID - SR TVC - 2016 - 213 dated 22.02.2016.Soil test report from IIT P alakad submitted to Divisional Railway Manager.Railway insisted the details of jacking force,number jacks its capacity and efficiency of jack,thrust bed/reaction bed details, rate of pushing,cutting edge etc the same submitted to railway. Contractor not willing do work and filed petition before hon high court, Work short closed Nattika Project Dn AE 2
29 Mar 2023 Laying work of 300mm DIK9 pipe is completed from Polemasterpadi to Pavaratty Jn.and 1380m length pipe laid. Total laying length of 300 mm is 6.60 km and total laying length of 250mm DIK9 is 2.30 km .Out of 13.8 km,total 8.90km laying completed .For the completion of work, it is necessary to obtain railway crossing permission. Application ID - SR TVC - 2016 - 213 dated 22.02.2016.Soil test report from IIT P alakad submitted to Divisional Railway Manager.Railway insisted the details of jacking force,number jacks its capacity and efficiency of jack,thrust bed/reaction bed details, rate of pushing,cutting edge etc the same submitted to railway. Contractor not willing do work and filed petition before hon high court, Work short closed Nattika Project Dn AE 2
28 Mar 2023 Laying work of 300mm DIK9 pipe is completed from Polemasterpadi to Pavaratty Jn.and 1380m length pipe laid. Total laying length of 300 mm is 6.60 km and total laying length of 250mm DIK9 is 2.30 km .Out of 13.8 km,total 8.90km laying completed .For the completion of work, it is necessary to obtain railway crossing permission. Application ID - SR TVC - 2016 - 213 dated 22.02.2016.Soil test report from IIT P alakad submitted to Divisional Railway Manager.Railway insisted the details of jacking force,number jacks its capacity and efficiency of jack,thrust bed/reaction bed details, rate of pushing,cutting edge etc the same submitted to railway. Contractor not willing do work and filed petition before hon high court Nattika Project Dn AE 2
27 Mar 2023 Laying work of 300mm DIK9 pipe is completed from Polemasterpadi to Pavaratty Jn.and 1380m length pipe laid. Total laying length of 300 mm is 6.60 km and total laying length of 250mm DIK9 is 2.30 km .Out of 13.8 km,total 8.90km laying completed .For the completion of work, it is necessary to obtain railway crossing permission. Application ID - SR TVC - 2016 - 213 dated 22.02.2016.Soil test report from IIT P alakad submitted to Divisional Railway Manager.Railway insisted the details of jacking force,number jacks its capacity and efficiency of jack,thrust bed/reaction bed details, rate of pushing,cutting edge etc the same submitted to railway. Contractor not willing do work and filed petition before hon high court Nattika Project Dn AE 2
26 Mar 2023 Laying work of 300mm DIK9 pipe is completed from Polemasterpadi to Pavaratty Jn.and 1380m length pipe laid. Total laying length of 300 mm is 6.60 km and total laying length of 250mm DIK9 is 2.30 km .Out of 13.8 km,total 8.90km laying completed .For the completion of work, it is necessary to obtain railway crossing permission. Application ID - SR TVC - 2016 - 213 dated 22.02.2016.Soil test report from IIT P alakad submitted to Divisional Railway Manager.Railway insisted the details of jacking force,number jacks its capacity and efficiency of jack,thrust bed/reaction bed details, rate of pushing,cutting edge etc the same submitted to railway. Contractor not willing do work and filed petition before hon high court Nattika Project Dn AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 12/03/2018
Scheduled date of Completion of the Project 17 May 2018
Expected date of Completion 30/08/2022

Processing Dates

AS Date 12 Oct 2017
TS Date 17 Sep 2016

Other details