Description |
WSS to Pavaratty and Mullassery Panchayath in Chavakkad Thaluk – Supplying, laying, testing and commissioning 300/250/200 mm DI K9 gravity main from Chattukulam to Pavaratty and Mullassery OHSR including Railway push through level cross at Brahmakulam |
Status |
On-going |
District |
Thrissur |
Executing Office |
Nattika Project Dn |
AS Amount (Rs) |
56176000
|
AS Number |
KWA/HO/W/TSR/TD/03/04/2017 |
TS Amount (Rs) |
136000000 |
TS Number |
TS/CE/CR/KWA/17/16-17 |
Total Bill Submitted (Rs) |
54819862 |
Total Bill Paid (Rs) |
27970000 |
Population Benefitted |
52081 |
Capacity in MLD |
33.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Pavaratty and Mullassery |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
WSS to Pavaratty and mullassery panchayath s - Gravity main |
Nattika Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Mar 2023 |
Laying work of 300mm DIK9 pipe is completed from Polemasterpadi to Pavaratty Jn.and 1380m length pipe laid. Total laying length of 300 mm is 6.60 km and total laying length of 250mm DIK9 is 2.30 km .Out of 13.8 km,total 8.90km laying completed .For the completion of work, it is necessary to obtain railway crossing permission. Application ID - SR TVC - 2016 - 213 dated 22.02.2016.Soil test report from IIT P alakad submitted to Divisional Railway Manager.Railway insisted the details of jacking force,number jacks its capacity and efficiency of jack,thrust bed/reaction bed details, rate of pushing,cutting edge etc the same submitted to railway. Contractor not willing do work and filed petition before hon high court, Work short closed |
Nattika Project Dn AE 2 |
|
29 Mar 2023 |
Laying work of 300mm DIK9 pipe is completed from Polemasterpadi to Pavaratty Jn.and 1380m length pipe laid. Total laying length of 300 mm is 6.60 km and total laying length of 250mm DIK9 is 2.30 km .Out of 13.8 km,total 8.90km laying completed .For the completion of work, it is necessary to obtain railway crossing permission. Application ID - SR TVC - 2016 - 213 dated 22.02.2016.Soil test report from IIT P alakad submitted to Divisional Railway Manager.Railway insisted the details of jacking force,number jacks its capacity and efficiency of jack,thrust bed/reaction bed details, rate of pushing,cutting edge etc the same submitted to railway. Contractor not willing do work and filed petition before hon high court, Work short closed |
Nattika Project Dn AE 2 |
|
28 Mar 2023 |
Laying work of 300mm DIK9 pipe is completed from Polemasterpadi to Pavaratty Jn.and 1380m length pipe laid. Total laying length of 300 mm is 6.60 km and total laying length of 250mm DIK9 is 2.30 km .Out of 13.8 km,total 8.90km laying completed .For the completion of work, it is necessary to obtain railway crossing permission. Application ID - SR TVC - 2016 - 213 dated 22.02.2016.Soil test report from IIT P alakad submitted to Divisional Railway Manager.Railway insisted the details of jacking force,number jacks its capacity and efficiency of jack,thrust bed/reaction bed details, rate of pushing,cutting edge etc the same submitted to railway. Contractor not willing do work and filed petition before hon high court |
Nattika Project Dn AE 2 |
|
27 Mar 2023 |
Laying work of 300mm DIK9 pipe is completed from Polemasterpadi to Pavaratty Jn.and 1380m length pipe laid. Total laying length of 300 mm is 6.60 km and total laying length of 250mm DIK9 is 2.30 km .Out of 13.8 km,total 8.90km laying completed .For the completion of work, it is necessary to obtain railway crossing permission. Application ID - SR TVC - 2016 - 213 dated 22.02.2016.Soil test report from IIT P alakad submitted to Divisional Railway Manager.Railway insisted the details of jacking force,number jacks its capacity and efficiency of jack,thrust bed/reaction bed details, rate of pushing,cutting edge etc the same submitted to railway. Contractor not willing do work and filed petition before hon high court |
Nattika Project Dn AE 2 |
|
26 Mar 2023 |
Laying work of 300mm DIK9 pipe is completed from Polemasterpadi to Pavaratty Jn.and 1380m length pipe laid. Total laying length of 300 mm is 6.60 km and total laying length of 250mm DIK9 is 2.30 km .Out of 13.8 km,total 8.90km laying completed .For the completion of work, it is necessary to obtain railway crossing permission. Application ID - SR TVC - 2016 - 213 dated 22.02.2016.Soil test report from IIT P alakad submitted to Divisional Railway Manager.Railway insisted the details of jacking force,number jacks its capacity and efficiency of jack,thrust bed/reaction bed details, rate of pushing,cutting edge etc the same submitted to railway. Contractor not willing do work and filed petition before hon high court |
Nattika Project Dn AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
12/03/2018 |
Scheduled date of Completion of the Project |
17 May 2018 |
Expected date of Completion |
30/08/2022 |
Processing Dates
AS Date |
12 Oct 2017 |
TS Date |
17 Sep 2016 |