Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT.2 - Karunagappally Municipality.-UWSS to Karunagappally Supplying, Laying 500 mm DI Clear Water Pumping Main from Kolathumukku Tank Site to Thacheyil mukku old tank site at Karunagappally Municipality

Project AMRUT.2 - Karunagappally Municipality.-UWSS to Karunagappally Supplying, Laying 500 mm DI Clear Water Pumping Main from Kolathumukku Tank Site to Thacheyil mukku old tank site at Karunagappally Municipality
Project Code KLMAMRUT 2022313852
Type Main project
Funding Agency AMRUT 2
Category AMRUT
Type of scheme Water Supply
Scheme
Description AMRUT.2 - Karunagappally Municipality.-UWSS to Karunagappally Supplying, Laying 500 mm DI Clear Water Pumping Main from Kolathumukku Tank Site to Thacheyil mukku old tank site at Karunagappally Municipality
Status On-going
District Kollam
Executing Office Kollam PH Dn
AS Amount (Rs) 171401000
AS Number G.O.(Rt)No.473/2023/LSGD
TS Amount (Rs) 144900000
TS Number WRD/KWA-CE(SR)/EST_TS/1108/2022_26_1_1
Total Bill Submitted (Rs) 1
Total Bill Paid (Rs) 1
Population Benefitted 80191
Capacity in MLD 10.00
Actual Project Completion Date Date is not specified
Coverage Enhancement of supply of 7561 existing connections. CWPM sufficient for entire Karunagappally municipality

Packages

No. Project Name Location View
1 AMRUT.2 - Karunagappally Municipality.-UWSS to Karunagappally Supplying, Laying 500 mm DI Clear Water Pumping Main from Kolathumukku Tank Site to Thacheyil mukku old tank site at Karunagappally Municipality Oachira PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 Technical bid opened Oachira AE
08 May 2024 Technical bid opened Oachira AE
06 May 2024 Technical bid opened on 23.04.2024 Oachira AE
02 May 2024 Technical bid opened on 23.04.2024 Oachira AE
27 Apr 2024 Technical bid opened on 23.04.2024 Oachira AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 23 Feb 2023
TS Date 11 May 2023

Other details

Project Officers View