Project | Deposit-Madayi panchayath-pipeline shifting at Vellachal |
---|---|
Project Code | KNRGOK112416914P1 |
Type | Package |
Main Project | Deposit-Madayi panchayath-pipeline shifting at Vellachal |
Funding Agency | GOK |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | 4215-01-800-89 |
Description | Deposit-Madayi panchayath-pipeline shifting at Vellachal |
Status | On-going |
District | Kannur |
Executing Office | Pilathra WS Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 110000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/22643/2024_26_1_1 |
Technical specification |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | Date is not specified |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | Date is not specified |
TS Date | 18 Nov 2024 |
---|---|
Estimate Approval | 18 Nov 2024 |
NIT Approval | 18 Nov 2024 |
Pilathara WS Sn - AE |
Date: 16/01/2025 |
Work has been completed | 100% Completed
100% complete..
Pilathara WS Sn - AE |
Date: 14/01/2025 |
Work has started | 0% Completed
work oder issued.