Deposit work-(20-21)-Nedumangad block Panchayath-Providing water supply pipeline extension in Konganamkode-Urilikunnu,Moonanakkuzhy-Paluvally,Vazhode,Kunninpuram areain Panavoor Panchayath and Vipprathala-Moozhinkkodu road,Devinagar,Aluvila,Konchira,Venkitta road in Vembayam Panchayath
Project |
Deposit work-(20-21)-Nedumangad block Panchayath-Providing water supply pipeline extension in Konganamkode-Urilikunnu,Moonanakkuzhy-Paluvally,Vazhode,Kunninpuram areain Panavoor Panchayath and Vipprathala-Moozhinkkodu road,Devinagar,Aluvila,Konchira,Venkitta road in Vembayam Panchayath |
Project Code |
TVMDEPO10205814 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work-(20-21)-Nedumangad block Panchayath-Providing water supply pipeline extension in Konganamkode-Urilikunnu,Moonanakkuzhy-Paluvally,Vazhode,Kunninpuram areain Panavoor Panchayath and Vipprathala-Moozhinkkodu road,Devinagar,Aluvila,Konchira,Venkitta road in Vembayam Panchayath |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Kallara Sn |
AS Amount (Rs) |
1204000
|
AS Number |
848/BP2/2020/NDD |
TS Amount (Rs) |
1204000 |
TS Number |
10234/2020-21 |
Total Bill Submitted (Rs) |
158482 |
Total Bill Paid (Rs) |
974318 |
Population Benefitted |
2000 |
Capacity in MLD |
0.20 |
Actual Project Completion Date |
19 Apr 2021 |
Coverage |
Konganamkode-Urilikunnu,Moonanakkuzhy-Paluvally,Vazhode,Kunninpuram area in Panavoor Panchayath and Vipprathala-Moozhinkkodu road,Devinagar,Aluvila,Konchira,Venkitta road in Vembayam Panchayath |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work-(20-21)-Nedumangad block Panchayath-Providing water supply pipeline extension in Konganamkode-Urilikunnu,Moonanakkuzhy-Paluvally,Vazhode,Kunninpuram areain Panavoor Panchayath and Vipprathala-Moozhinkkodu road,Devinagar,Aluvila,Konchira,Venkitta road in Vembayam Panchayath |
Kallara Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
12 Apr 2022 |
Bill submitted |
Kallara AE |
|
11 Mar 2022 |
Bill submitted |
Kallara AE |
|
21 Jan 2022 |
Bill submitted |
Kallara AE |
|
20 Jan 2022 |
Bill submitted |
Kallara AE |
|
13 Jan 2022 |
Bill submitted |
Kallara AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
16/12/2020 |
Scheduled date of Completion of the Project |
17 Apr 2021 |
Expected date of Completion |
30/06/2022 |
Processing Dates
AS Date |
15 Oct 2020 |
TS Date |
30 Oct 2020 |