Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM 5th Phase-Head works Aruvikkara - Supplying, Erecting and commissioning of submersible pump set for additional pumping from common clear water sump of 86 & 74 MLD WTP.

Project JJM 5th Phase-Head works Aruvikkara - Supplying, Erecting and commissioning of submersible pump set for additional pumping from common clear water sump of 86 & 74 MLD WTP.
Project Code TVMGOK02209648
Type Main project
Funding Agency GOK
Category JJM
Type of scheme Water Supply
Scheme 2215-02-106-97
Description JJM 5th Phase-Head works Aruvikkara - Supplying, Erecting and commissioning of submersible pump set for additional pumping from common clear water sump of 86 & 74 MLD WTP.
Status Completed
District Thiruvananthapuram
Executing Office Aruvikkara Sn 3
AS Amount (Rs) 245300000
AS Number GO(Rt)No.134/2022/WRD
TS Amount (Rs) 1024000
TS Number 22895/2021-2022
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs)
Population Benefitted 1500000
Capacity in MLD 6.00
Actual Project Completion Date Date is not specified
Coverage Trivandrum Corporation Rural and Urban Areas
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM 5th Phase-Head works Aruvikkara - Supplying, Erecting and commissioning of submersible pump set for additional pumping from common clear water sump of 86 & 74 MLD WTP. Aruvikkara Sn 3

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Jun 2022 Work Completed Aruvikkara Sn 3 AE
15 Jun 2022 1.Existing MCCB @ Pump House replaced during the shut down work (11-06-2022) & laying of cables completed 2. Pump & Motor Erected and trial run conducted successfully on 11-06-2022 3. Marked the position for constructing anchor block on the top of clear water sump Aruvikkara Sn 3 AE
01 Jun 2022 30 % Work Completed- 1. All the material arrived at the site& started the work 2. Erection of Pump and motor started 3. CMG Note submitted for Shut Down permission for installing panel panel board (For replacing existing MCCB and laying of incomer & Outgoing Cables) Aruvikkara Sn 3 AE
26 May 2022 Work Order Issued. Pump and Motor arrived at contractor's work site along with valves. MS pipe fabrication ongoing. Installation to be done once electrical and mechanical parts are ready at the site. Aruvikkara WS Sub Dn AEE
27 Apr 2022 Work Order Issued Aruvikkara WS Sub Dn AEE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 05/04/2022
Scheduled date of Completion of the Project 20 Apr 2022
Expected date of Completion 04/06/2022

Processing Dates

AS Date 23 Feb 2022
TS Date 14 Mar 2022

Other details

Project Officers View