Jal Jeevan Mission - CWSS to Kalippara - Water supply line extension & providing water connections from existing and proposed pipelines to households of Vellarada Grama Panchayath under Kattakkada WS Section-(Phase-2)
Project |
Jal Jeevan Mission - CWSS to Kalippara - Water supply line extension & providing water connections from existing and proposed pipelines to households of Vellarada Grama Panchayath under Kattakkada WS Section-(Phase-2) |
Project Code |
TVMJJM08208706 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission - CWSS to Kalippara - Water supply line extension & providing water connections from existing and proposed pipelines to households of Vellarada Grama Panchayath under Kattakkada WS Section-(Phase-2) |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Kattakada WS Sn |
AS Amount (Rs) |
204352000
|
AS Number |
GO(Rt).No.541/2020/WRD |
TS Amount (Rs) |
179100000 |
TS Number |
TS/2021-2022/2019/22284 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
32800 |
Capacity in MLD |
36.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Vellarada GP |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM- 2020-2021 Providing functional house hold tape connection at Malayinkavu coleny under vellarda GPu |
Kattakada WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
04 Jun 2022 |
TVMJJM08208706 |
Neyyattinkara AEE |
|
04 Jun 2022 |
completed |
Neyyattinkara AEE |
|
04 Jun 2022 |
completed |
Kattakkada WS Sn AE |
|
04 Jun 2022 |
Non starter |
Kattakkada WS Sn AE |
|
02 Jun 2022 |
Non starter |
Kattakkada WS Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/11/2021 |
Scheduled date of Completion of the Project |
31 Mar 2024 |
Expected date of Completion |
31/03/2024 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |