JJM 2020-2021-Chenkal Grama panchayath - Phase 2

Project JJM 2020-2021-Chenkal Grama panchayath - Phase 2
Project Code TVMJJM08205577P1
Type Package
Main Project JJM 2020-21 Thiruvananthapuram District Chenkal Grama Panchayath- Prroviding pipe line extension and House hold connections in Chenkal Grama Panchayath - 1000 FHTCs
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description JJM 2020-2021-Chenkal Grama panchayath - Phase 2
Status Completed
District Thiruvananthapuram
Executing Office Parassala WS Sn
Agreement Number
Agreement Date
TS Amount (Rs) 11800000
TS Number TS/2020-2021/2020/15443
Technical specification 1000 water connections can be provided by pipeline extensions after the augmentation of the scheme such as replacing of damaged pipelines and providing for house hold connections by conducting hydraulic feasibility survey for preparing distribution net work map (GIS),making soft drawings for further minor pipeline extensions in densely populated areas facing shortage of drinking water.
Contractor T J SIMON (Mob: 9447656590)

Project Review

See All Review messages
Review Date Review Message Review Attended By
28 May 2021 the work is delayed due to Covid-19 Executive Engineer
10 Feb 2021 Ongoing Executive Engineer

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 29/09/2020
Scheduled date of Completion as per agreement 29 Mar 2021
Expected date of Completion 31/03/2022

Processing Dates

TS Date 26 Aug 2020
Estimate Approval 26 Aug 2020
NIT Approval 26 Aug 2020
Tender Closing 17 Sep 2020
Technichal Pre-Qualification 16 Sep 2020
Price bid opening 19 Sep 2020

Approval Dates

Workorder Date 29 Sep 2020
NA 16 Oct 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Parassala WS Sn
Date: 25/07/2022

Work has been completed | 100% Completed

Work has been completed 800 FHTC COMPLETED.

Parassala WS Sn
Date: 24/07/2022

Work has been completed | 100% Completed

Work has been completed 800 FHTC COMPLETED.