Project | KCH-WS-03:- Rehabiltation of Distribution and Service Connections in SA road |
---|---|
Project Code | EKMADB07113008P6 |
Type | Package |
Main Project | ADB Assisted KSUDP Water Supply Scheme |
Funding Agency | ADB |
Category | ADB assisted KSUD Project |
Type of scheme | Water Supply |
Scheme | |
Description | Rehabiltation of Distribution and Service Connections in SA road |
Status | Completed |
District | Ernakulam |
Executing Office | Kochi Project Division |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | |
TS Number | |
Technical specification | Rehabiltation of Distribution and Service Connections in SA road |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 08/12/2011 |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | 06/12/2013 |
Workorder Date | 09 Nov 2011 |
---|---|
NA | 08 Dec 2011 |
Kochi WS Project Dn AEE-2 |
Date: 04/02/2021 |
Work in progress | 100% Completed
short closed.
Kochi WS Project Dn AEE-2 |
Date: 09/09/2020 |
Work in progress | 10% Completed
Work preclosed.