- Home
- DEPOSIT-CWSS to Clappana Grama panchayat...
DEPOSIT-CWSS to Clappana Grama panchayath -Disconnection of Public taps in Clappana Grama Panchayath-General Civil Work
Project |
DEPOSIT-CWSS to Clappana Grama panchayath -Disconnection of Public taps in Clappana Grama Panchayath-General Civil Work |
Project Code |
KLMDEPO082212690 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
DEPOSIT-CWSS to Clappana Grama panchayath -Disconnection of Public taps in Clappana Grama Panchayath-General Civil Work |
Status |
Completed |
District |
Kollam |
Executing Office |
Chavara PH Sub Dn |
AS Amount (Rs) |
396000
|
AS Number |
SC1-731/2022 |
TS Amount (Rs) |
392000 |
TS Number |
WRD/KWA-CE(SR)/EST-TS/7991/2022-5-1-1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1000 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
27 Jan 2023 |
Coverage |
Disconnection of Public taps in Clappana Grama Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-CWSS to Clappana Grama panchayath -Disconnection of Public taps in Clappana Grama Panchayath-General Civil Work |
Oachira PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
06 Feb 2023 |
Work completed and final bill submitted |
Oachira AE |
|
04 Feb 2023 |
work completed bill under preparation |
Oachira AE |
|
01 Feb 2023 |
work completed bill under preparation |
Oachira AE |
|
30 Jan 2023 |
work completed bill under preparation |
Chavara AEE |
|
27 Jan 2023 |
Work completed |
Oachira AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
Date is not specified |
Scheduled date of Completion of the Project |
04 Feb 2023 |
Expected date of Completion |
04/02/2023 |
Processing Dates
AS Date |
02 Aug 2022 |
TS Date |
03 Nov 2022 |