State Plan 2023-24-UWSS to Kothamangalam Municipality- Supplying, erection and commissioning of one 40 HP CF Pumpset and allied works in Kothamangalam CWPH No. 1 in Kothamangalam Municipality.

Project State Plan 2023-24-UWSS to Kothamangalam Municipality- Supplying, erection and commissioning of one 40 HP CF Pumpset and allied works in Kothamangalam CWPH No. 1 in Kothamangalam Municipality.
Project Code EKMGOK052314472P1
Type Package
Main Project State Plan 2023-24-UWSS to Kothamangalam Municipality- Supplying, erection and commissioning of one 40 HP CF Pumpset and allied works in Kothamangalam CWPH No. 1 in Kothamangalam Municipality.
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan 2023-24-UWSS to Kothamangalam Municipality- Supplying, erection and commissioning of one 40 HP CF Pumpset and allied works in Kothamangalam CWPH No. 1 in Kothamangalam Municipality.
Status On-going
District Ernakulam
Executing Office Kothamangalam Sn 1
Agreement Number
Agreement Date
TS Amount (Rs) 1610000
TS Number TS/5398/2023_5_2_1 dated 01/11/2023 Reg No.17859/2023-2024
Technical specification Supplying, erection and commissioning of one 40 HP CF Pumpset and allied works in Kothamangalam CWPH No. 1 in Kothamangalam Municipality.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 12/12/2023
Scheduled date of Completion as per agreement 11 Jun 2024
Expected date of Completion Date is not specified

Processing Dates

TS Date 01 Nov 2023
Estimate Approval 01 Nov 2023
NIT Approval 01 Nov 2023
Tender Closing 15 Nov 2023
Technichal Pre-Qualification 15 Nov 2023
Price bid opening 17 Nov 2023

Approval Dates

Workorder Date 27 Nov 2023
NA 12 Dec 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kothamangalam PH Sn 1 - AE
Date: 20/04/2024

Work in progress | 30% Completed

Induction motor and pump reached at site.

Kothamangalam PH Sn 1 - AE
Date: 15/03/2024

Work has started | 0% Completed

Agreement executed.