Deposit work -2021-22 - Laying of 90mm PVC pipe line at Murikungal Ward 5, Replacing existing damaged PVC pipe line with 90mm PVC pipe at Nooluvalli in ward 10 of Mattathur Grama Panchayath.
Project |
Deposit work -2021-22 - Laying of 90mm PVC pipe line at Murikungal Ward 5, Replacing existing damaged PVC pipe line with 90mm PVC pipe at Nooluvalli in ward 10 of Mattathur Grama Panchayath. |
Project Code |
TCRDEPO042213334 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work -2021-22 - Laying of 90mm PVC pipe line at Murikungal Ward 5, Replacing existing damaged PVC pipe line with 90mm PVC pipe at Nooluvalli in ward 10 of Mattathur Grama Panchayath. |
Status |
Completed |
District |
Thrissur |
Executing Office |
Chalakkudy PH Sn |
AS Amount (Rs) |
2500000
|
AS Number |
A2-2041/22 |
TS Amount (Rs) |
2500000 |
TS Number |
TS/9641/2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
750 |
Capacity in MLD |
0.06 |
Actual Project Completion Date |
Date is not specified |
Coverage |
100% |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work -2021-22 - Laying of 90mm PVC pipe line at Murikungal Ward 5, Replacing existing damaged PVC pipe line with 90mm PVC pipe at Nooluvalli in ward 10 of Mattathur Grama Panchayath |
Chalakkudy PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 May 2023 |
work completed,bill submitted |
Chalakudy AE 1 |
|
18 Apr 2023 |
work completed |
Chalakudy AE 1 |
|
17 Apr 2023 |
Pipe laying progressing in ward 1 |
Chalakudy AE 1 |
|
13 Apr 2023 |
Pipe laying progressing in ward 1 |
Chalakudy AE 1 |
|
10 Apr 2023 |
Pipe laying progressing in ward 1 |
Chalakudy AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
11/01/2023 |
Scheduled date of Completion of the Project |
31 May 2023 |
Expected date of Completion |
31/05/2023 |
Processing Dates
AS Date |
28 Apr 2022 |
TS Date |
09 Dec 2022 |