| Project | Automation of Submersible Pumps-Stand by Pump sets in RWSS to Vilamana,RWSS to Ayirakkalam, RWSS to Meethaley Punnad and RWSS to Sankarankandy. |
|---|---|
| Project Code | KNRRKI032214710P1 |
| Type | Package |
| Main Project | Automation of Submersible Pumps-Stand by Pump sets in RWSS to Vilamana,RWSS to Ayirakkalam, RWSS to Meethaley Punnad and RWSS to Sankarankandy. |
| Funding Agency | RKI |
| Category | RKI |
| Type of scheme | Water Supply |
| Scheme | 5475-00-115-94-05 |
| Description | Rebuild-Automation of Submersible Pumps in Kerala Water Authority Implementation of Phase I (Stage 1&2) Park under RKI- Automation of Stand by Pump Sets in RWSS to Vilamana,RWSS to Ayirakkalam, RWSS to Meethaley Punnad and RWSS to Sankarankandy. |
| Status | On-going |
| District | Kannur |
| Executing Office | Chavasseryparamba WS Sn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 190000 |
| TS Number | WRD/KWA-CE(NR)/EST-TS/5357/2022_6_1_1 |
| Technical specification | Rebuild-Automation of Submersible Pumps in Kerala Water Authority Implementation of Phase I (Stage 1&2) Park under RKI- Automation of Stand by Pump Sets in RWSS to Vilamana,RWSS to Ayirakkalam, RWSS to Meethaley Punnad and RWSS to Sankarankandy. |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 17/06/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 03 Jul 2023 |
| Expected date of Completion | 03/07/2023 |
| TS Date | 18 Mar 2023 |
|---|---|
| Estimate Approval | 15 Mar 2023 |
| NIT Approval | 18 Mar 2023 |
| Tender Closing | 18 Mar 2023 |
| Technichal Pre-Qualification | 18 Mar 2023 |
| Price bid opening | 18 Mar 2023 |
| Workorder Date | 23 May 2023 |
|---|---|
| NA | 17 Jun 2023 |
| Chavasseryparamba WS Sn AE |
| Date: 05/08/2023 |
Work has been completed | 100% Completed
Bill Submitted.
| Chavasseryparamba WS Sn AE |
| Date: 21/07/2023 |
Work has been completed | 100% Completed
work completed,Bill under Preparation.