Deposit work of Kalpetta municipality- Pipe line extension to various wards from UIDSSMT WSS to Kalpetta Muncipality
Project |
Deposit work of Kalpetta municipality- Pipe line extension to various wards from UIDSSMT WSS to Kalpetta Muncipality |
Project Code |
WYDDEPO022011563 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work of Kalpetta municipality- Pipe line extension to various wards from UIDSSMT WSS to Kalpetta Muncipality |
Status |
Completed |
District |
Wayanad |
Executing Office |
Kalpetta PH Sn 1 |
AS Amount (Rs) |
8865000
|
AS Number |
E3-1726/2022,E-3-11865/19 |
TS Amount (Rs) |
8800000 |
TS Number |
TS/2022-2023/2022/13275 |
Total Bill Submitted (Rs) |
6793042 |
Total Bill Paid (Rs) |
6793042 |
Population Benefitted |
1000 |
Capacity in MLD |
10.00 |
Actual Project Completion Date |
31 Dec 2022 |
Coverage |
Kalpetta municipality |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work of Kalpetta municipality- Pipe line extension to various wards from UIDSSMT WSS to Kalpetta Muncipality |
Kalpetta PH Sn 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Mar 2023 |
Bill submitted to division office |
Kalpetta PH Sn 1 - AE |
|
10 Feb 2023 |
Bill submitted to subdivision |
Kalpetta PH Sn 1 - AE |
|
24 Jan 2023 |
Work completed . Bill under preparation. |
Sulthan Bathery PH Dn EE |
|
16 Jan 2023 |
valve chamber works |
Kalpetta PH Sn 1 - AE |
|
14 Jan 2023 |
valve chamber works |
Kalpetta PH Sn 1 - AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
09/06/2022 |
Scheduled date of Completion of the Project |
31 Dec 2022 |
Expected date of Completion |
31/12/2022 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
09 Jun 2022 |