KRFB- 2017-18 IMPROVEMENT TO PEERUMEDU, DEVIKULAM ROADS IN IDUKKI DIST. - SHIFTING OF KWA UTILITIES- Idukkikavala - Nariyampara
Project |
KRFB- 2017-18 IMPROVEMENT TO PEERUMEDU, DEVIKULAM ROADS IN IDUKKI DIST. - SHIFTING OF KWA UTILITIES- Idukkikavala - Nariyampara |
Project Code |
IDKGOK112213331 |
Type |
Main project |
Funding Agency |
GOK |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Improvement works to Peerumedu - Devikulam Road |
Status |
On-going |
District |
Idukki |
Executing Office |
Kattappana Project Dn |
AS Amount (Rs) |
50359930
|
AS Number |
KRFB-PMU/MVPA-IDK/HH-PD/2021 |
TS Amount (Rs) |
27860000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/12798/2022_26_1_1 |
Total Bill Submitted (Rs) |
5474620 |
Total Bill Paid (Rs) |
5474620 |
Population Benefitted |
53000 |
Capacity in MLD |
7.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Kanchiyar Panchayath & Kattappana Muncipality |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT-KRFB-Hill Highway KRFB- Shifting of KWA utilities- Idukkikavala - Nariyampara |
Project Division Kattapana |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
12 May 2024 |
On-going with excavation of trenches and re-laying of pipes. Completed 3069.435 meters of 250mm DI and 23.25 meters of 250mm MS pipe laying. |
Kattappana AEE 1 |
|
09 May 2024 |
On-going with excavation of trenches and re-laying of pipes. Completed 3069.435 meters of 250mm DI and 23.25 meters of 250mm MS pipe laying. |
Kattappana AEE 1 |
|
06 May 2024 |
On-going with excavation of trenches and re-laying of pipes. Completed 3069.435 meters of 250mm DI and 23.25 meters of 250mm MS pipe laying. |
Kattappana AEE 1 |
|
03 May 2024 |
On-going with excavation of trenches and re-laying of pipes. Completed 3069.435 meters of 250mm DI and 23.25 meters of 250mm MS pipe laying. |
Kattappana AEE 1 |
|
30 Apr 2024 |
On-going with excavation of trenches and re-laying of pipes. Completed 3069.435 meters of 250mm DI and 12 meters of 250mm MS pipe laying. |
Kattappana AEE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
15/01/2023 |
Scheduled date of Completion of the Project |
10 Aug 2023 |
Expected date of Completion |
15/04/2023 |
Processing Dates
AS Date |
01 Nov 2022 |
TS Date |
09 Dec 2022 |