Improving water supply by laying 110mm PVC Pipe towards Paruthippara X Lane in Nalanchira Ward
Project |
Improving water supply by laying 110mm PVC Pipe towards Paruthippara X Lane in Nalanchira Ward |
Project Code |
TVMDEPO062212194 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work of Thiruvananthapuram Corporation -Project No-S0548/22- Improving water supply by laying 110mm PVC Pipe towards Paruthippara X Lane in Nalanchira Ward |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Pongumoodu Sn(Maintenance) |
AS Amount (Rs) |
497000
|
AS Number |
J4/548/21 |
TS Amount (Rs) |
497000 |
TS Number |
7705/2022-2023 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
100 |
Capacity in MLD |
0.03 |
Actual Project Completion Date |
26 Oct 2022 |
Coverage |
coverage 100 people. laying 110mm PVC Pipe for a length of 214m |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Improving water supply by laying 110mm PVC Pipe towards Paruthippara X Lane in Nalanchira Ward |
Pongumoodu Sn(Maintenance) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 Dec 2022 |
completed |
Pongummoodu Sn AE |
|
05 Dec 2022 |
completed |
Pongummoodu Sn AE |
|
16 Nov 2022 |
work started |
Pongummoodu Sn AE |
|
08 Nov 2022 |
not started |
Pongummoodu Sn AE |
|
31 Oct 2022 |
not started |
Pongummoodu Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
28/07/2022 |
Scheduled date of Completion of the Project |
27 Oct 2022 |
Expected date of Completion |
27/10/2022 |
Processing Dates
AS Date |
08 Jun 2022 |
TS Date |
18 Jun 2022 |