Project | Deposit work Under PWD/ KRFB-KWA Utility Shifting- Relaying of Existing Distribution lines along Thekkada to Mukkampalamoodu road in connection with Mangalapuram-Pazhakutty road widening project of by KIIFB(Reach-1) |
---|---|
Project Code | TVMKIIFB10218356P1 |
Type | Package |
Main Project | Deposit work Under PWD/ KRFB-KWA Utility Shifting- Relaying of Existing Distribution lines along Pazhakutty- Mangalapuram road widening project by KIIFB |
Funding Agency | DEPO |
Category | PWD Deposit |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Deposit work Under PWD/ KRFB-KWA Utility Shifting- Relaying of Existing Distribution lines along Thekkada to Mukkampalamoodu road in connection with Mangalapuram-Pazhakutty road widening project of by KIIFB(Reach-1) |
Status | On-going |
District | Thiruvananthapuram |
Executing Office | Kallara Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 7357000 |
TS Number | 14608/2021-2022 |
Technical specification | Deposit work Under PWD/ KRFB-KWA Utility Shifting |
Contractor | M Subair (Mob: 8281621466) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 19/01/2022 |
---|---|
Scheduled date of Completion as per agreement | 21 May 2022 |
Expected date of Completion | 30/06/2022 |
TS Date | 03 Dec 2021 |
---|---|
Estimate Approval | 03 Dec 2021 |
NIT Approval | 03 Dec 2021 |
Tender Closing | 10 Dec 2021 |
Technichal Pre-Qualification | 14 Dec 2021 |
Price bid opening | 14 Dec 2021 |
Workorder Date | 19 Jan 2022 |
---|---|
NA | 25 Jan 2022 |
Kallara AE |
Date: 06/01/2023 |
Work in progress | 98% Completed
Work completed except construction of valve chambers. Valve chamber construction going on.
Aruvikkara HW Dn EE |
Date: 03/01/2023 |
Work in progress | 98% Completed
Work completed except construction of valve chambers. Valve chamber construction going on.