Deposit work 2020-2021:-Paippad Grama Panchayath-Extension of pipe line and providing street tap in various wards,Nakralputhuvel Mangalasserypady to Nakra Kizhakekara at ward.No.15 and Moolayil Puthuvel road of ward No.01

Project Deposit work 2020-2021:-Paippad Grama Panchayath-Extension of pipe line and providing street tap in various wards,Nakralputhuvel Mangalasserypady to Nakra Kizhakekara at ward.No.15 and Moolayil Puthuvel road of ward No.01
Project Code KTMDEPO112011960
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work 2020-2021:-Paippad Grama Panchayath-Extension of pipe line and providing street tap in various wards,Nakralputhuvel Mangalasserypady to Nakra Kizhakekara at ward.No.15 and Moolayil Puthuvel road of ward No.01
Status Completed
District Kottayam
Executing Office Changanassery Sn
AS Amount (Rs) 1810000
AS Number A3.2979/2020 Dt:28.02.2022 -1210000/-, A3.2979/2020 Dt:11.01.2020 -250000/-, A3.2979/2020 Dt: 14.10.2020- 350000/-
TS Amount (Rs) 1810000
TS Number TS/2022-2023/2021/9664 Dt:16.05.2022- 1210000/-, TS/2022-2023/2021/2230 Dt:16.05.2022- 250000/-, TS/2022-2023/2021/2365 Dt:16.05.2022- 350000/-
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 4500
Capacity in MLD 0.25
Actual Project Completion Date 07 Oct 2022
Coverage Pipeline extension
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work 2020-2021:-Paippad Grama Panchayath-Extension of pipe line and providing street tap in various wards,Nakralputhuvel Mangalasserypady to Nakra Kizhakekara at ward.No.15 and Moolayil Puthuvel road of ward No.01 Changanassery Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Sep 2022 The places where the work to be done are located next to the AC road & canal the entire area is now flooded and work can be done only once the climate become favourable-when paddy fields are drained for farming Changanaserry PH Sn - AE
30 Aug 2022 The places where the work to be done are located next to the AC road & canal the entire area is now flooded and work can be done only once the climate become favourable Changanaserry PH Sn - AE
25 Aug 2022 Agreement executed Changanaserry PH Sub Dn - AEE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 11/01/2020
Scheduled date of Completion of the Project 07 Oct 2022
Expected date of Completion 07/10/2022

Processing Dates

AS Date 11 Jan 2020
TS Date 16 May 2022

Other details

Project Officers View