- Home
- JICA Assisted Water Supply Scheme -The S...
JICA Assisted Water Supply Scheme -The Supply and Installation of Electromagnetic Flow meters With Central Data Acquisition System
Project |
JICA Assisted Water Supply Scheme -The Supply and Installation of Electromagnetic Flow meters With Central Data Acquisition System |
Project Code |
TVMGOK10096056 |
Type |
Main project |
Funding Agency |
GOK |
Category |
JICA projects |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
The Supply and Installation of Electromagnetic Flow meters With Central Data Acquisition System |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
JICA project |
AS Amount (Rs) |
101400000
|
AS Number |
G.O.(Rt.)No.1175/09/WRD |
TS Amount (Rs) |
|
TS Number |
|
Total Bill Submitted (Rs) |
38563297 |
Total Bill Paid (Rs) |
30910260 |
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
JICA Assisted Water Supply Project -Institutional Strengthening-The Supply and Installation of Electromagnetic Flow meters With Central Data Acquisition System |
JICA |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
04 Jun 2022 |
Work terminated |
PIU 4- AE -18 - JICA |
|
22 Feb 2021 |
Vide letter No. KWA/JICA/CE/IS-4518/14 Dated: 17.02.2021 . CE (P&O) issued Final Termination Notice to M/s YIL |
PIU 4 - AE 19 - JICA |
|
27 Jan 2021 |
62 locations out of 147 completed.
|
PIU 4 - AE 19 - JICA |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
12/03/2014 |
Scheduled date of Completion of the Project |
11 Mar 2015 |
Expected date of Completion |
31/12/2020 |
Processing Dates
AS Date |
20 Oct 2019 |
TS Date |
12 Aug 2013 |